Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,660
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0239 # 09 Y:2000 | 09 | 2000 | PURCHASE EQUIPMENT INSTEAD OF LEASING | $6,856 | $7,990 | Not Implemented |
IA0239 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $364 | $0 | Not Implemented |
IA0238 # 01 Y:2000 | 01 | 2000 | INSTALL STEAM TRAP | $1,500 | $628 | Implemented |
IA0238 # 02 Y:2000 | 02 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,337 | $6,470 | Not Implemented |
IA0238 # 03 Y:2000 | 03 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,072 | $363 | Not Implemented |
IA0238 # 04 Y:2000 | 04 | 2000 | INSULATE BARE EQUIPMENT | $485 | $195 | Not Implemented |
IA0238 # 05 Y:2000 | 05 | 2000 | USE ONLY AMOUNT OF PACKAGING MATERIAL NECESSARY | $8,476 | $21,000 | Not Implemented |
IA0232 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,704 | $13,064 | Not Implemented |
IA0232 # 02 Y:1999 | 02 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,087 | $445 | Not Implemented |
IA0232 # 03 Y:1999 | 03 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,827 | $537 | Implemented |
IA0232 # 04 Y:1999 | 04 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $704 | $828 | Not Implemented |
IA0232 # 05 Y:1999 | 05 | 1999 | CONVERT TO ELECTROSTATIC POWDER COATING | $150,000 | $28,000 | Not Implemented |
IA0232 # 06 Y:1999 | 06 | 1999 | RECYCLE CLEANING SOLVENT AND REUSE | $33,891 | $10,300 | Implemented |
IA0232 # 07 Y:1999 | 07 | 1999 | CLOSELY MONITOR CHEMICAL ADDITIONS TO INCREASE BATH LIFE | $9,540 | $16,088 | Not Implemented |
IA0232 # 08 Y:1999 | 08 | 1999 | MOVE PRODUCT USING MECHANICAL MEANS | $31,898 | $175,500 | Not Implemented |
IA0237 # 01 Y:1999 | 01 | 1999 | RECOVER WASTE HEAT FROM EQUIPMENT | $6,880 | $1,142 | Not Implemented |
IA0237 # 02 Y:1999 | 02 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,608 | $945 | Not Implemented |
IA0237 # 03 Y:1999 | 03 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,447 | $264 | Not Implemented |
IA0237 # 04 Y:1999 | 04 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,914 | $8,729 | Not Implemented |
IA0237 # 05 Y:1999 | 05 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,891 | $0 | Not Implemented |
IA0237 # 06 Y:1999 | 06 | 1999 | INSTALL OCCUPANCY SENSORS | $247 | $466 | Not Implemented |
IA0237 # 07 Y:1999 | 07 | 1999 | DISTILL CONTAMINATED SOLVENTS FOR REUSE | $7,704 | $10,300 | Not Implemented |
IA0237 # 08 Y:1999 | 08 | 1999 | INSTALL SYSTEM TO COLLECT SCRAP | $47,034 | $3,932 | Not Implemented |
IA0227 # 01 Y:1999 | 01 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $825,660 | $1,863 | n/a |
IA0227 # 02 Y:1999 | 02 | 1999 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $66,200 | $2,000 | n/a |