Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,929
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0858 # 06 Y:2023 | 06 | 2023 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $106 | $375 | n/a |
MA0858 # 05 Y:2023 | 05 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $204 | $264 | n/a |
MA0858 # 03 Y:2023 | 03 | 2023 | USE HEAT PUMP FOR SPACE CONDITIONING | $12,269 | $11,300 | n/a |
MA0857 # 02 Y:2023 | 02 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,193 | $200 | n/a |
MA0857 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $93,363 | $714,951 | n/a |
MA0857 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $481 | $192 | n/a |
MA0857 # 04 Y:2023 | 04 | 2023 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $200 | $131 | n/a |
MA0856 # 05 Y:2023 | 05 | 2023 | USE HEAT PUMP FOR SPACE CONDITIONING | $1,091 | $385 | n/a |
MA0856 # 03 Y:2023 | 03 | 2023 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $859 | $900 | n/a |
MA0856 # 02 Y:2023 | 02 | 2023 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $7,517 | $23,709 | n/a |
MA0856 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $47,289 | $222,915 | n/a |
MA0856 # 04 Y:2023 | 04 | 2023 | USE HEAT PUMP FOR SPACE CONDITIONING | $2,528 | $1,450 | n/a |
MA0855 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $63,886 | $285,949 | n/a |
MA0855 # 04 Y:2023 | 04 | 2023 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $1,302 | $900 | n/a |
MA0855 # 02 Y:2023 | 02 | 2023 | USE HEAT PUMP FOR SPACE CONDITIONING | $3,299 | $22,900 | n/a |
MA0855 # 06 Y:2023 | 06 | 2023 | USE HEAT PUMP FOR SPACE CONDITIONING | $988 | $385 | n/a |
MA0855 # 03 Y:2023 | 03 | 2023 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $10,616 | $23,709 | n/a |
MA0855 # 05 Y:2023 | 05 | 2023 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $747 | $550 | n/a |
MA0852 # 06 Y:2023 | 06 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,244 | $1,866 | Not Implemented |
MA0852 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $99,365 | $854,943 | Implemented |
MA0852 # 03 Y:2023 | 03 | 2023 | RECOVER WASTE HEAT FROM EQUIPMENT | $22,824 | $33,749 | Not Implemented |
MA0852 # 04 Y:2023 | 04 | 2023 | USE EXISTING DAM TO GENERATE ELECTRICITY | $20,149 | $203,280 | Not Implemented |
MA0852 # 07 Y:2023 | 07 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,597 | $875 | Not Implemented |
MA0852 # 05 Y:2023 | 05 | 2023 | INCREASE EFFICIENCY OF TRUCKS | $10,205 | $546,530 | Not Implemented |
MA0852 # 08 Y:2023 | 08 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,591 | $1,544 | Implemented |