Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,985
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0380 # 04 Y:2008 | 04 | 2008 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $168,000 | $120,000 | Not Implemented |
NC0380 # 05 Y:2008 | 05 | 2008 | IMPROVE SPACE COMFORT CONDITIONING | $89,762 | $37,500 | Not Implemented |
NC0380 # 06 Y:2008 | 06 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $16,126 | $91,580 | Not Implemented |
NC0380 # 07 Y:2008 | 07 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $138 | $980 | Not Implemented |
NC0380 # 08 Y:2008 | 08 | 2008 | DEVELOP A REPAIR/REPLACE POLICY | $1,283 | $1,540 | Implemented |
NC0376 # 01 Y:2008 | 01 | 2008 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $12,423 | $15,000 | Not Implemented |
NC0376 # 02 Y:2008 | 02 | 2008 | ADJUST BURNERS FOR EFFICIENT OPERATION | $44,894 | $1,000 | Implemented |
NC0376 # 03 Y:2008 | 03 | 2008 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $32,459 | $75,000 | Implemented |
NC0376 # 04 Y:2008 | 04 | 2008 | FLASH CONDENSATE TO PRODUCE LOWER PRESSURE STEAM | $42,026 | $7,815 | Not Implemented |
NC0376 # 05 Y:2008 | 05 | 2008 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $21,163 | $50 | Not Implemented |
NC0376 # 06 Y:2008 | 06 | 2008 | RECOVER WASTE HEAT FROM EQUIPMENT | $12,635 | $3,500 | Not Implemented |
NC0376 # 07 Y:2008 | 07 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $400 | $100 | Implemented |
NC0376 # 08 Y:2008 | 08 | 2008 | DEVELOP A REPAIR/REPLACE POLICY | $4,903 | $7,820 | Implemented |
NC0376 # 09 Y:2008 | 09 | 2008 | USE PHOTOCELL CONTROLS | $2,567 | $1,900 | Implemented |
NC0376 # 10 Y:2008 | 10 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $229 | $507 | Not Implemented |
NC0377 # 01 Y:2008 | 01 | 2008 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $1,484 | $2,800 | Implemented |
NC0377 # 02 Y:2008 | 02 | 2008 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,040 | $1,000 | Implemented |
NC0377 # 03 Y:2008 | 03 | 2008 | DEVELOP A REPAIR/REPLACE POLICY | $475 | $930 | Implemented |
NC0377 # 04 Y:2008 | 04 | 2008 | RECOVER WASTE HEAT FROM EQUIPMENT | $5,415 | $11,000 | Not Implemented |
NC0377 # 05 Y:2008 | 05 | 2008 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $595 | $100 | Implemented |
NC0377 # 06 Y:2008 | 06 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $26,040 | $111,342 | Implemented |
NC0377 # 07 Y:2008 | 07 | 2008 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,691 | $1,495 | Implemented |
NC0375 # 01 Y:2008 | 01 | 2008 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,790 | $7,000 | Not Implemented |
NC0375 # 02 Y:2008 | 02 | 2008 | UTILIZE OTHER METHODS TO REMOVE CONTAMINANTS | $15,885 | $41,750 | Not Implemented |
NC0375 # 03 Y:2008 | 03 | 2008 | INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT | $3,903 | $7,500 | Implemented |