Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,843
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
NC0623 # 04 Y:2018 | 04 | 2018 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $6,478 | $16,800 | Implemented |
NC0623 # 03 Y:2018 | 03 | 2018 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,320 | $1,203 | Implemented |
NC0623 # 01 Y:2018 | 01 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,801 | $500 | Implemented |
NC0622 # 09 Y:2018 | 09 | 2018 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $15,903 | $500 | Implemented |
NC0622 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,414 | $525 | Implemented |
NC0622 # 02 Y:2018 | 02 | 2018 | INSTALL OCCUPANCY SENSORS | $481 | $250 | Implemented |
NC0622 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,812 | $46,617 | Implemented |
NC0616 # 09 Y:2018 | 09 | 2018 | AVOID REWINDING MOTORS MORE THAN TWICE | $2,586 | $5,865 | Implemented |
NC0616 # 08 Y:2018 | 08 | 2018 | REDESIGN PROCESS | $36,741 | $2,500 | Implemented |
NC0616 # 07 Y:2018 | 07 | 2018 | INSTALL SENSORS TO DETECT DEFECTS | $112,500 | $150,000 | Implemented |
NC0616 # 05 Y:2018 | 05 | 2018 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,999 | $100 | Implemented |
NC0616 # 03 Y:2018 | 03 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $505 | $50 | Implemented |
NC0616 # 02 Y:2018 | 02 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,695 | $225 | Implemented |
NC0616 # 01 Y:2018 | 01 | 2018 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,771 | $43,490 | Implemented |
NC0620 # 05 Y:2018 | 05 | 2018 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $927 | $1,000 | Implemented |
NC0620 # 03 Y:2018 | 03 | 2018 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,426 | $100 | Implemented |
NC0620 # 01 Y:2018 | 01 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,189 | $2,250 | Implemented |
NC0619 # 09 Y:2018 | 09 | 2018 | AVOID REWINDING MOTORS MORE THAN TWICE | $3,477 | $5,865 | Implemented |
NC0619 # 08 Y:2018 | 08 | 2018 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $25,721 | $500 | Implemented |
NC0619 # 04 Y:2018 | 04 | 2018 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,718 | $1,800 | Implemented |
NC0619 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,617 | $100 | Implemented |
NC0619 # 02 Y:2018 | 02 | 2018 | INSTALL OCCUPANCY SENSORS | $211 | $350 | Implemented |
NC0614 # 03 Y:2018 | 03 | 2018 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,801 | $200 | Implemented |
NC0614 # 02 Y:2018 | 02 | 2018 | INSTALL OCCUPANCY SENSORS | $190 | $350 | Implemented |
NC0615 # 10 Y:2018 | 10 | 2018 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $282 | $50 | Implemented |