Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
837
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OD0120 # 04 Y:1998 | 04 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $246,500 | $180,480 | Implemented |
OD0117 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,497 | $7,621 | Not Implemented |
OD0117 # 02 Y:1998 | 02 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $127 | $608 | Implemented |
OD0117 # 03 Y:1998 | 03 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,198 | $920 | Implemented |
OD0117 # 04 Y:1998 | 04 | 1998 | INSTALL OCCUPANCY SENSORS | $375 | $100 | Implemented |
OD0117 # 05 Y:1998 | 05 | 1998 | METER WASTE WATER | $6,227 | $4,595 | Implemented |
OD0117 # 06 Y:1998 | 06 | 1998 | PAY BILLS ON TIME TO AVOID LATE FEES | $5,823 | $0 | Implemented |
OD0116 # 01 Y:1998 | 01 | 1998 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $2,986 | $1,615 | Not Implemented |
OD0116 # 02 Y:1998 | 02 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $925 | $2,175 | Implemented |
OD0116 # 03 Y:1998 | 03 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $921 | $800 | Implemented |
OD0116 # 04 Y:1998 | 04 | 1998 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $95 | $91 | Implemented |
OD0116 # 05 Y:1998 | 05 | 1998 | USE SYNTHETIC LUBRICANT | $255 | $255 | Implemented |
OD0115 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $479 | $765 | n/a |
OD0115 # 02 Y:1998 | 02 | 1998 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $42 | $83 | n/a |
OD0115 # 03 Y:1998 | 03 | 1998 | KEEP BOILER TUBES CLEAN | $140 | $150 | n/a |
OD0115 # 04 Y:1998 | 04 | 1998 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $12,000 | $700 | n/a |
OD0114 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,198 | $1,457 | Implemented |
OD0114 # 02 Y:1998 | 02 | 1998 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $143 | $80 | Implemented |
OD0114 # 03 Y:1998 | 03 | 1998 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $35 | $10 | Implemented |
OD0114 # 04 Y:1998 | 04 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,303 | $509 | Implemented |
OD0114 # 05 Y:1998 | 05 | 1998 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,123 | $50 | Not Implemented |
OD0114 # 06 Y:1998 | 06 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $538 | $1,010 | Not Implemented |
OD0114 # 07 Y:1998 | 07 | 1998 | ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL | $17,428 | $9,180 | Not Implemented |
OD0112 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,091 | $8,577 | Implemented |
OD0112 # 02 Y:1998 | 02 | 1998 | REPAIR OR REPLACE STEAM TRAPS | $4,912 | $990 | Implemented |