Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,019
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0622 # 01 Y:2001 | 01 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $8,626 | $2,120 | Implemented |
OK0622 # 02 Y:2001 | 02 | 2001 | INSTALL ADEQUATE DRYERS ON AIR LINES TO ELIMINATE BLOWDOWN | $6,659 | $1,089 | Implemented |
OK0622 # 03 Y:2001 | 03 | 2001 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,700 | $654 | Implemented |
OK0622 # 04 Y:2001 | 04 | 2001 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,944 | $100 | Not Implemented |
OK0622 # 05 Y:2001 | 05 | 2001 | INSTALL SET-BACK TIMERS | $2,788 | $288 | Not Implemented |
OK0622 # 06 Y:2001 | 06 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $70,100 | $152,055 | Implemented |
OK0622 # 07 Y:2001 | 07 | 2001 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $635,180 | $125,000 | Implemented |
OK0530 # 01 Y:1997 | 01 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,605 | $0 | n/a |
OK0530 # 02 Y:1997 | 02 | 1997 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $4,324 | $7,801 | n/a |
OK0530 # 03 Y:1997 | 03 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $594 | $548 | n/a |
OK0530 # 04 Y:1997 | 04 | 1997 | INSTALL SET-BACK TIMERS | $734 | $252 | n/a |
OK0530 # 05 Y:1997 | 05 | 1997 | USE BATCH FIRING WITH KILN "FURNITURE" SPECIFICALLY DESIGNED | $172 | $0 | n/a |
OK0530 # 06 Y:1997 | 06 | 1997 | MOVE PRODUCT USING MECHANICAL MEANS | $24,230 | $60,000 | n/a |
OK0530 # 07 Y:1997 | 07 | 1997 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $548 | $1,040 | n/a |
OK0530 # 08 Y:1997 | 08 | 1997 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $4,096 | $8,570 | n/a |
OK0528 # 01 Y:1997 | 01 | 1997 | USE FLUE GASES TO HEAT PROCESS OR SERVICE WATER | $17,998 | $48,754 | Implemented |
OK0528 # 02 Y:1997 | 02 | 1997 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $6,011 | $3,500 | Implemented |
OK0528 # 03 Y:1997 | 03 | 1997 | USE WASTE HEAT FROM HOT FLUE GASES TO GENERATE STEAM | $3,099 | $4,655 | Not Implemented |
OK0528 # 04 Y:1997 | 04 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $962 | $114 | Implemented |
OK0528 # 05 Y:1997 | 05 | 1997 | USE OPTIMUM THICKNESS INSULATION | $747 | $166 | Implemented |
OK0528 # 06 Y:1997 | 06 | 1997 | SEPARATE AND RECYCLE SCRAP METAL TO FOUNDRY OR FOR SALE | $6,149 | $12,500 | Not Implemented |
OK0528 # 07 Y:1997 | 07 | 1997 | MOVE PRODUCT USING MECHANICAL MEANS | $39,936 | $28,000 | Not Implemented |
OK0498 # 01 Y:1996 | 01 | 1996 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,692 | $3,200 | Implemented |
OK0498 # 02 Y:1996 | 02 | 1996 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,469 | $1,648 | Implemented |
OK0498 # 03 Y:1996 | 03 | 1996 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,649 | $1,399 | Not Implemented |