Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
122
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0659 # 04 Y:2015 | 04 | 2015 | INSULATE BARE EQUIPMENT | $6,192 | $8,000 | Implemented |
OR0659 # 03 Y:2015 | 03 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $906 | $900 | Not Implemented |
OR0659 # 02 Y:2015 | 02 | 2015 | MINIMIZE CONTAMINATION OF WATER BEFORE TREATMENT | $26,260 | $7,200 | Implemented |
OR0659 # 01 Y:2015 | 01 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $10,705 | $20,000 | Implemented |
OR0658 # 04 Y:2015 | 04 | 2015 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $20,781 | $0 | Not Implemented |
OR0658 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $54,203 | $59,203 | Implemented |
OR0658 # 02 Y:2015 | 02 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $680,062 | $427,000 | Implemented |
OR0658 # 01 Y:2015 | 01 | 2015 | MODIFY CURRENT INCENTIVE PROGRAM | $22,712 | $60,000 | Not Implemented |
OR0657 # 01 Y:2015 | 01 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $48,205 | $50,205 | Implemented |
OR0657 # 03 Y:2015 | 03 | 2015 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $207,496 | $694,826 | Not Implemented |
OR0657 # 02 Y:2015 | 02 | 2015 | INSULATE BARE EQUIPMENT | $24,174 | $32,596 | Not Implemented |
OR0656 # 05 Y:2015 | 05 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,282 | $22,500 | Implemented |
OR0656 # 04 Y:2015 | 04 | 2015 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $317,386 | $0 | Not Implemented |
OR0656 # 03 Y:2015 | 03 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,591 | $27,789 | Implemented |
OR0656 # 02 Y:2015 | 02 | 2015 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $188,688 | $247,000 | Implemented |
OR0656 # 01 Y:2015 | 01 | 2015 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $2,308,919 | $1,300,000 | Implemented |
OR0653 # 05 Y:2015 | 05 | 2015 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $4,262 | $15,398 | Not Implemented |
OR0655 # 09 Y:2015 | 09 | 2015 | USE SOLAR HEAT TO MAKE ELECTRICTY | $2,480 | $20,979 | Not Implemented |
OR0655 # 08 Y:2015 | 08 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $4,958 | $7,816 | Not Implemented |
OR0655 # 07 Y:2015 | 07 | 2015 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $51,916 | $126,000 | Not Implemented |
OR0655 # 06 Y:2015 | 06 | 2015 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $180,695 | $251,760 | Not Implemented |
OR0655 # 05 Y:2015 | 05 | 2015 | FLASH CONDENSATE TO PRODUCE LOWER PRESSURE STEAM | $15,571 | $19,050 | Not Implemented |
OR0653 # 03 Y:2015 | 03 | 2015 | USE OPTIMUM THICKNESS INSULATION | $3,897 | $4,580 | Not Implemented |
OR0655 # 03 Y:2015 | 03 | 2015 | TURN OFF EQUIPMENT WHEN NOT IN USE | $20,211 | $1,000 | Not Implemented |
OR0655 # 02 Y:2015 | 02 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $4,161 | $1,000 | Implemented |