Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
33
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0696 # 04 Y:2017 | 04 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,910 | $10,116 | Not Implemented |
OR0696 # 02 Y:2017 | 02 | 2017 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $79,265 | $37,275 | Not Implemented |
OR0696 # 01 Y:2017 | 01 | 2017 | DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS | $179,573 | $3,044 | Not Implemented |
OR0696 # 03 Y:2017 | 03 | 2017 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $2,365 | $5,880 | Not Implemented |
OR0695 # 03 Y:2017 | 03 | 2017 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $12,279 | $43,386 | Implemented |
OR0695 # 02 Y:2017 | 02 | 2017 | USE COLD WASTE WATER TO COOL CHILLER FEED WATER | $13,796 | $30,600 | Not Implemented |
OR0695 # 01 Y:2017 | 01 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,343 | $10,981 | Not Implemented |
OR0694 # 06 Y:2017 | 06 | 2017 | MINIMIZE WATER USAGE | $8,079 | $15,125 | Not Implemented |
OR0694 # 05 Y:2017 | 05 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,605 | $10,606 | Not Implemented |
OR0694 # 04 Y:2017 | 04 | 2017 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $29,962 | $12,100 | Not Implemented |
OR0694 # 03 Y:2017 | 03 | 2017 | INSTALL BACK-UP EQUIPMENT | $219,130 | $45,000 | Not Implemented |
OR0694 # 02 Y:2017 | 02 | 2017 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $78,503 | $7,018 | Not Implemented |
OR0694 # 01 Y:2017 | 01 | 2017 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $190,250 | $7,842 | Not Implemented |
OR0692 # 01 Y:2017 | 01 | 2017 | REDUCE FLUID FLOW RATES | $26,801 | $7,395 | Not Implemented |
OR0692 # 02 Y:2017 | 02 | 2017 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $2,636 | $3,060 | Not Implemented |
OR0692 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,299 | $3,670 | Not Implemented |
OR0689 # 01 Y:2017 | 01 | 2017 | PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST | $12,509 | $19,000 | Implemented |
OR0689 # 02 Y:2017 | 02 | 2017 | PREVENT EXCESSIVE SOLVENT USAGE (OPERATOR TRAINING) | $18,000 | $1,495 | Implemented |
OR0689 # 03 Y:2017 | 03 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,595 | $5,595 | Implemented |
OR0689 # 04 Y:2017 | 04 | 2017 | REDUCE VENTILATION AIR | $3,492 | $12,558 | Not Implemented |
OR0687 # 05 Y:2017 | 05 | 2017 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $6,460 | $16,124 | Not Implemented |
OR0687 # 04 Y:2017 | 04 | 2017 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $3,195 | $5,650 | Not Implemented |
OR0687 # 03 Y:2017 | 03 | 2017 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $205,629 | $340,000 | Not Implemented |
OR0687 # 02 Y:2017 | 02 | 2017 | USE PHOTOCELL CONTROLS | $2,967 | $2,000 | Not Implemented |
OR0687 # 01 Y:2017 | 01 | 2017 | ADJUST BURNERS FOR EFFICIENT OPERATION | $2,090 | $600 | Not Implemented |