IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

263

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
SD0265 # 04 Y:2001 04 2001 UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT $1,874 $1,012 Implemented
SD0265 # 05 Y:2001 05 2001 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $4,783 $12,500 Not Implemented
SD0265 # 06 Y:2001 06 2001 MAINTAIN MACHINES TO REDUCE LEAKS $1,771 $0 Implemented
SD0264 # 01 Y:2001 01 2001 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $28,141 $61,000 Not Implemented
SD0264 # 02 Y:2001 02 2001 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $26,759 $27,900 Not Implemented
SD0264 # 03 Y:2001 03 2001 TURN OFF EQUIPMENT WHEN NOT IN USE $2,117 $735 Not Implemented
SD0264 # 04 Y:2001 04 2001 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $3,654 $7,900 Not Implemented
SD0264 # 05 Y:2001 05 2001 $1,812 $5,500 Not Implemented
SD0263 # 01 Y:2001 01 2001 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $8,376 $20,000 Not Implemented
SD0263 # 02 Y:2001 02 2001 TURN OFF EQUIPMENT WHEN NOT IN USE $1,258 $1,500 Implemented
SD0263 # 03 Y:2001 03 2001 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $3,173 $4,000 Implemented
SD0263 # 04 Y:2001 04 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,402 $90 Implemented
SD0263 # 05 Y:2001 05 2001 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $5,644 $9,576 Implemented
SD0263 # 06 Y:2001 06 2001 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT $3,239 $4,250 Not Implemented
SD0263 # 07 Y:2001 07 2001 USE LESS TOXIC AND VOLATILE SOLVENT SUBSTITUTES $4,278 $0 Implemented
SD0263 # 08 Y:2001 08 2001 $52,000 $60,000 Not Implemented
SD0263 # 09 Y:2001 09 2001 $9,500 $7,000 Implemented
SD0262 # 01 Y:2001 01 2001 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $34,244 $92,000 Not Implemented
SD0262 # 02 Y:2001 02 2001 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $112,352 $179,000 Not Implemented
SD0262 # 03 Y:2001 03 2001 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $18,419 $15,000 Not Implemented
SD0262 # 04 Y:2001 04 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $5,942 $300 Not Implemented
SD0262 # 05 Y:2001 05 2001 $38,254 $1,700 Not Implemented
SD0262 # 06 Y:2001 06 2001 INSULATE BARE EQUIPMENT $12,581 $5,200 Not Implemented
SD0262 # 07 Y:2001 07 2001 REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT $24,738 $40,000 Not Implemented
SD0262 # 08 Y:2001 08 2001 INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS $5,300 $7,900 Not Implemented