IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

166

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
TT0319 # 08 Y:2024 08 2024 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $497 $32 n/a
TT0319 # 07 Y:2024 07 2024 TURN OFF EQUIPMENT WHEN NOT IN USE $4,402 $3,250 n/a
TT0319 # 06 Y:2024 06 2024 INSTALL OCCUPANCY SENSORS $4,645 $900 n/a
TT0319 # 05 Y:2024 05 2024 INSTALL TIMERS AND/OR THERMOSTATS $5,922 $7,350 n/a
TT0319 # 04 Y:2024 04 2024 CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE $6,842 $0 n/a
TT0319 # 03 Y:2024 03 2024 KEEP DOORS AND WINDOWS SHUT WHEN NOT ON USE $9,169 $0 n/a
TT0319 # 02 Y:2024 02 2024 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $21,264 $88,000 n/a
TT0319 # 01 Y:2024 01 2024 USE SOLAR HEAT TO MAKE ELECTRICTY $46,802 $502,083 n/a
TT0301 # 06 Y:2023 06 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $7,899 $1,500 Implemented
TT0301 # 05 Y:2023 05 2023 SUBSTITUTE COMPRESSED AIR COOLING WITH WATER OR AIR COOLING $8,886 $220 Implemented
TT0301 # 04 Y:2023 04 2023 TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME $9,607 $0 Implemented
TT0301 # 03 Y:2023 03 2023 REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT $32,720 $15,200 Implemented
TT0301 # 02 Y:2023 02 2023 BURN FOSSIL FUEL TO PRODUCE STEAM TO DRIVE A STEAM TURBINE-GENERATOR AND USE STEAM EXHAUST FOR HEAT $40,702 $210,000 Not Implemented
TT0301 # 01 Y:2023 01 2023 USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT $47,506 $76,760 Not Implemented
TT0291 # 02 Y:2023 02 2023 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $41,378 $10,100 Implemented
TT0291 # 01 Y:2023 01 2023 RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER $44,264 $3,287 Not Implemented
TT0291 # 03 Y:2023 03 2023 PURCHASE APPROPRIATELY SIZED MATERIAL $18,022 $87,000 Not Implemented
TT0291 # 05 Y:2023 05 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $9,663 $1,500 Implemented
TT0291 # 04 Y:2023 04 2023 USE OPTIMUM THICKNESS INSULATION $14,929 $45,390 Not Implemented
TT0291 # 06 Y:2023 06 2023 INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS $2,088 $4,500 Not Implemented
TT0241 # 04 Y:2020 04 2020 REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT $18,441 $75,000 Implemented
TT0241 # 06 Y:2020 06 2020 UPGRADE CONTROLS ON COMPRESSORS $4,203 $120 Not Implemented
TT0241 # 05 Y:2020 05 2020 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $8,106 $530 Implemented
TT0241 # 01 Y:2020 01 2020 RECOVER WASTE HEAT FROM EQUIPMENT $116,047 $13,220 Not Implemented
TT0241 # 03 Y:2020 03 2020 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $49,818 $14,600 Implemented