Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

7,108

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UD1028 # 07 Y:2021 07 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $807 $0 Not Implemented
UD1028 # 08 Y:2021 08 2021 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $210 $600 Not Implemented
UD1028 # 09 Y:2021 09 2021 INSTALL OCCUPANCY SENSORS $3,730 $5,760 Not Implemented
UD1027 # 01 Y:2021 01 2021 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $1,612 $0 Implemented
UD1027 # 02 Y:2021 02 2021 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $11,486 $1,000 Not Implemented
UD1027 # 03 Y:2021 03 2021 RECOVER AND REUSE COOLING WATER $7,993 $0 Not Implemented
UD1027 # 04 Y:2021 04 2021 ELIMINATE OR REDUCE COMPRESSED AIR USAGE $2,522 $0 Not Implemented
UD1027 # 05 Y:2021 05 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $1,842 $1,000 Implemented
UD1027 # 06 Y:2021 06 2021 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $1,443 $0 Not Implemented
UD1027 # 07 Y:2021 07 2021 REPAIR OR REPLACE STEAM TRAPS $6,067 $4,875 Not Implemented
UD1027 # 08 Y:2021 08 2021 AVOID COOLING OF PROCESS STREAMS OR MATERIALS THAT MUST SUBSEQUENTLY BE HEATED $2,481 $4,300 Not Implemented
UD1027 # 09 Y:2021 09 2021 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $17,013 $65,250 Implemented
UD1027 # 10 Y:2021 10 2021 INSTALL MOTOR VOLTAGE CONTROLLER ON LIGHTLY LOADED MOTORS $10,735 $43,000 Not Implemented
UD1026 # 01 Y:2021 01 2021 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,601 $0 Implemented
UD1026 # 02 Y:2021 02 2021 INSTALL OUTSIDE AIR DAMPER / ECONOMIZER ON HVAC UNIT $174,302 $45,000 Implemented
UD1026 # 03 Y:2021 03 2021 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $58,812 $45,000 Not Implemented
UD1026 # 04 Y:2021 04 2021 USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING $441,982 $200,000 Not Implemented
UD1026 # 05 Y:2021 05 2021 UTILIZE A LESS EXPENSIVE COOLING METHOD $42,343 $88,894 Implemented
UD1026 # 06 Y:2021 06 2021 CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE $817 $0 Not Implemented
UD1025 # 01 Y:2020 01 2020 REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS $2,747 $0 Not Implemented
UD1025 # 02 Y:2020 02 2020 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $16,051 $340 Implemented
UD1025 # 03 Y:2020 03 2020 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,411 $4,000 Not Implemented
UD1025 # 04 Y:2020 04 2020 INSULATE BARE EQUIPMENT $83,809 $25,133 Not Implemented
UD1025 # 05 Y:2020 05 2020 REDUCE EXCESSIVE BOILER BLOWDOWN $6,710 $5,224 Not Implemented
UD1025 # 06 Y:2020 06 2020 COMBINE UTILITY METERS $8,278 $0 Not Implemented