Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,161
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UF0585 # 02 Y:2022 | 02 | 2022 | INCREASE AMOUNT OF CONDENSATE RETURNED | $11,758 | $1,342 | Implemented |
UF0585 # 01 Y:2022 | 01 | 2022 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $21,858 | $44,939 | Implemented |
UF0584 # 10 Y:2022 | 10 | 2022 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $68,493 | $0 | Implemented |
UF0584 # 07 Y:2022 | 07 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $9,855 | $40,432 | Implemented |
UF0583 # 04 Y:2022 | 04 | 2022 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $13,240 | $0 | Implemented |
UF0583 # 01 Y:2022 | 01 | 2022 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $308,276 | $1,243,750 | Implemented |
UF0583 # 02 Y:2022 | 02 | 2022 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $44,987 | $62,001 | Implemented |
UF0583 # 03 Y:2022 | 03 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,746 | $33,000 | Implemented |
UF0582 # 12 Y:2022 | 12 | 2022 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $333,010 | $0 | Implemented |
UF0582 # 10 Y:2022 | 10 | 2022 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $16,853 | $7,275 | Implemented |
UF0582 # 08 Y:2022 | 08 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $22,408 | $756 | Implemented |
UF0582 # 06 Y:2022 | 06 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $37,793 | $79,204 | Implemented |
UF0582 # 04 Y:2022 | 04 | 2022 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $226,296 | $102,253 | Implemented |
UF0581 # 07 Y:2022 | 07 | 2022 | LEVEL ONE – ADD COMMUNICATION USING IIOT DEVICES TO EXISTING CONTROL SYSTEM TO MODIFY OPERATIONS | $2,191 | $0 | Implemented |
UF0581 # 06 Y:2022 | 06 | 2022 | LEVEL THREE - INSTALL OR MODIFY CONTROL SYSTEM WITH COMMUNICATION AND NONLOCAL EXTERNAL INFORMATION (I.E. WEATHER FORECA | $3,458 | $11,225 | Implemented |
UF0581 # 05 Y:2022 | 05 | 2022 | LEVEL ZERO – INSTALL CONTROL SYSTEMS FOR EXISTING EQUIPMENT | $11,526 | $10,000 | Implemented |
UF0581 # 04 Y:2022 | 04 | 2022 | INSTALL SOFT-START TO ELIMINATE NUISANCE TRIPS | $5,091 | $8,250 | Implemented |
UF0581 # 03 Y:2022 | 03 | 2022 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $8,046 | $5,794 | Implemented |
UF0581 # 02 Y:2022 | 02 | 2022 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $17,084 | $4,202 | Implemented |
UF0580 # 09 Y:2022 | 09 | 2022 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,516 | $594 | Implemented |
UF0580 # 08 Y:2022 | 08 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,370 | $10,501 | Implemented |
UF0580 # 07 Y:2022 | 07 | 2022 | INSTALL OCCUPANCY SENSORS | $3,037 | $2,270 | Implemented |
UF0580 # 06 Y:2022 | 06 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,465 | $8,588 | Implemented |
UF0580 # 04 Y:2022 | 04 | 2022 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $11,115 | $20,214 | Implemented |
UF0580 # 03 Y:2022 | 03 | 2022 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $18,832 | $31,696 | Implemented |