Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,094
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0455 # 01 Y:2015 | 01 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,635 | $2,000 | Not Implemented |
UM0455 # 02 Y:2015 | 02 | 2015 | INSTALL OR UPGRADE INSULATION ON HVAC DISTRIBUTION SYSTEMS | $8,778 | $0 | Not Implemented |
UM0455 # 03 Y:2015 | 03 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,898 | $500 | Implemented |
UM0455 # 04 Y:2015 | 04 | 2015 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $6,274 | $7,300 | Implemented |
UM0455 # 05 Y:2015 | 05 | 2015 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,338 | $2,500 | Implemented |
UM0455 # 06 Y:2015 | 06 | 2015 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $11,725 | $25,000 | Not Implemented |
UM0454 # 01 Y:2015 | 01 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,028 | $2,000 | Not Implemented |
UM0454 # 02 Y:2015 | 02 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,291 | $14,700 | Not Implemented |
UM0454 # 03 Y:2015 | 03 | 2015 | CHANGE ZONE REHEAT COILS TO VARIABLE AIR VOLUME BOXES | $2,130 | $1,710 | Implemented |
UM0454 # 04 Y:2015 | 04 | 2015 | USE WASTE HEAT FROM HOT FLUE GASES TO GENERATE STEAM | $13,892 | $4,500 | Not Implemented |
UM0454 # 05 Y:2015 | 05 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,354 | $1,000 | Not Implemented |
UM0453 # 01 Y:2015 | 01 | 2015 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $19,380 | $5,000 | Not Implemented |
UM0453 # 02 Y:2015 | 02 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,831 | $1,000 | Implemented |
UM0453 # 03 Y:2015 | 03 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,442 | $1,500 | Implemented |
UM0453 # 04 Y:2015 | 04 | 2015 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $10,115 | $5,400 | Not Implemented |
UM0453 # 05 Y:2015 | 05 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $7,852 | $4,000 | Implemented |
UM0452 # 01 Y:2015 | 01 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,871 | $1,000 | Not Implemented |
UM0452 # 02 Y:2015 | 02 | 2015 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,393 | $2,500 | Implemented |
UM0452 # 03 Y:2015 | 03 | 2015 | RECYCLE AIR FOR HEATING, VENTILATION AND AIR CONDITIONING | $28,779 | $28,000 | Implemented |
UM0452 # 04 Y:2015 | 04 | 2015 | RECOVER WASTE HEAT FROM EQUIPMENT | $2,903 | $4,000 | Implemented |
UM0451 # 01 Y:2014 | 01 | 2014 | OPTIMIZE PLANT POWER FACTOR | $16,165 | $25,000 | Implemented |
UM0451 # 02 Y:2014 | 02 | 2014 | INSTALL OCCUPANCY SENSORS | $6,320 | $4,800 | Implemented |
UM0451 # 03 Y:2014 | 03 | 2014 | REVISE SMOKE CLEANUP FROM OPERATIONS | $79,670 | $60,000 | Not Implemented |
UM0451 # 04 Y:2014 | 04 | 2014 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $3,930 | $6,000 | Not Implemented |
UM0450 # 01 Y:2014 | 01 | 2014 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $58,763 | $200,000 | Not Implemented |