Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,732
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UM0127 # 04 Y:1999 | 04 | 1999 | USE FILTRATION, CENTRIFUGING TO REMOVE CONTAMINANTS | $30,552 | $35,000 | Not Implemented |
UM0127 # 05 Y:1999 | 05 | 1999 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $12,705 | $13,600 | Not Implemented |
UM0126 # 01 Y:1998 | 01 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,401 | $25,843 | Implemented |
UM0126 # 02 Y:1998 | 02 | 1998 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $5,221 | $938 | Not Implemented |
UM0126 # 03 Y:1998 | 03 | 1998 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $20,053 | $5,250 | Implemented |
UM0126 # 04 Y:1998 | 04 | 1998 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $24,729 | $250 | Not Implemented |
UM0126 # 05 Y:1998 | 05 | 1998 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $21,553 | $80,000 | Not Implemented |
UM0126 # 06 Y:1998 | 06 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $862 | $1,000 | Implemented |
UM0126 # 07 Y:1998 | 07 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $9,603 | $2,000 | Implemented |
UM0126 # 08 Y:1998 | 08 | 1998 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,264 | $1,800 | Implemented |
UM0126 # 09 Y:1998 | 09 | 1998 | RECOVER AND REUSE COOLING WATER | $6,202 | $4,500 | Implemented |
UM0126 # 10 Y:1998 | 10 | 1998 | INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM | $200,000 | $0 | Implemented |
UM0126 # 11 Y:1998 | 11 | 1998 | CLEAR AND RENT EXISTING SPACE | $151,198 | $5,000 | Not Implemented |
UM0125 # 01 Y:1998 | 01 | 1998 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $12,144 | $250 | Implemented |
UM0125 # 02 Y:1998 | 02 | 1998 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $47,135 | $3,000 | Implemented |
UM0125 # 03 Y:1998 | 03 | 1998 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $89,497 | $25,000 | Implemented |
UM0125 # 04 Y:1998 | 04 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $250,120 | $1,500,000 | Not Implemented |
UM0125 # 05 Y:1998 | 05 | 1998 | INSTALL BACK-UP EQUIPMENT | $11,544 | $24,180 | Not Implemented |
UM0120 # 01 Y:1998 | 01 | 1998 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,335 | $250 | Not Implemented |
UM0120 # 02 Y:1998 | 02 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,860 | $1,000 | Implemented |
UM0120 # 03 Y:1998 | 03 | 1998 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $8,029 | $1,000 | Implemented |
UM0120 # 04 Y:1998 | 04 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,783 | $100 | Implemented |
UM0120 # 05 Y:1998 | 05 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $962 | $1,500 | Not Implemented |
UM0120 # 06 Y:1998 | 06 | 1998 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $14,994 | $5,000 | Not Implemented |
UM0120 # 07 Y:1998 | 07 | 1998 | IMPROVE SPACE COMFORT CONDITIONING | $1,440 | $518 | Implemented |