IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,094

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UM0157 # 03 Y:2000 03 2000 REDUCE EXCESSIVE BOILER BLOWDOWN $1,224 $4,430 Implemented
UM0157 # 04 Y:2000 04 2000 REGRIND, REUSE, OR SELL SCRAP PLASTIC PARTS $8,000 $400 Not Implemented
UM0157 # 05 Y:2000 05 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $1,296 $738 Implemented
UM0156 # 01 Y:2000 01 2000 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $428 $500 Implemented
UM0156 # 02 Y:2000 02 2000 DISCONNECT BALLASTS $1,786 $0 Implemented
UM0156 # 03 Y:2000 03 2000 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $10,860 $48,600 Not Implemented
UM0156 # 04 Y:2000 04 2000 REDUCE EXCESSIVE BOILER BLOWDOWN $1,813 $4,430 Not Implemented
UM0156 # 05 Y:2000 05 2000 REPAIR OR REPLACE STEAM TRAPS $9,420 $880 Implemented
UM0156 # 06 Y:2000 06 2000 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $7,640 $6,500 Implemented
UM0156 # 07 Y:2000 07 2000 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $19,310 $7,000 Not Implemented
UM0156 # 08 Y:2000 08 2000 CHANGE OPERATING CONDITIONS $38,942 $20,000 Not Implemented
UM0155 # 01 Y:2000 01 2000 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $575 $500 Implemented
UM0155 # 02 Y:2000 02 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,279 $300 Implemented
UM0155 # 03 Y:2000 03 2000 INSTALL / REPAIR INSULATION ON STEAM LINES $664 $309 Implemented
UM0155 # 04 Y:2000 04 2000 USE "HEAT WHEEL" OR OTHER HEAT EXCHANGER TO CROSS-EXCHANGE BUILDING EXHAUST AIR WITH MAKE-UP AIR $5,751 $18,000 Not Implemented
UM0155 # 05 Y:2000 05 2000 RECOVER AND REUSE COOLING WATER $31,455 $21,257 Implemented
UM0154 # 01 Y:2000 01 2000 DISCONNECT BALLASTS $2,608 $880 Implemented
UM0154 # 02 Y:2000 02 2000 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $732 $1,400 Not Implemented
UM0154 # 03 Y:2000 03 2000 RECOVER WASTE HEAT FROM EQUIPMENT $7,312 $25,370 Not Implemented
UM0154 # 04 Y:2000 04 2000 REDUCE VENTILATION AIR $18,794 $0 Implemented
UM0154 # 05 Y:2000 05 2000 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE $9,360 $0 Implemented
UM0154 # 06 Y:2000 06 2000 ADD ADDITIONAL PRODUCTION SHIFT $1,980,000 $568,714 Not Implemented
UM0153 # 01 Y:2000 01 2000 UTILIZE A LESS EXPENSIVE COOLING METHOD $4,796 $2,000 Not Implemented
UM0153 # 02 Y:2000 02 2000 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $1,023 $800 Not Implemented
UM0153 # 03 Y:2000 03 2000 REUSE SCRAP GLASS AS FEED STOCK $7,831 $0 Not Implemented