Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,483
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UU0260 # 06 Y:2024 | 06 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $489 | $1,818 | n/a |
UU0260 # 05 Y:2024 | 05 | 2024 | TURN OFF EQUIPMENT DURING BREAKS, REDUCE OPERATING TIME | $726 | $3,000 | n/a |
UU0260 # 04 Y:2024 | 04 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,557 | $6,277 | n/a |
UU0260 # 03 Y:2024 | 03 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,696 | $8,277 | n/a |
UU0260 # 02 Y:2024 | 02 | 2024 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $10,585 | $5,800 | n/a |
UU0260 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $27,825 | $247,680 | n/a |
UU0261 # 06 Y:2024 | 06 | 2024 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $400 | $5,940 | n/a |
UU0261 # 05 Y:2024 | 05 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $1,386 | $8,280 | n/a |
UU0261 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,063 | $9,140 | n/a |
UU0261 # 03 Y:2024 | 03 | 2024 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $12,100 | $21,600 | n/a |
UU0261 # 02 Y:2024 | 02 | 2024 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $2,592 | $37,200 | n/a |
UU0261 # 01 Y:2024 | 01 | 2024 | USE SOLAR HEAT TO MAKE ELECTRICTY | $22,296 | $572,100 | n/a |
UU0258 # 01 Y:2024 | 01 | 2024 | INSTALL SMALLER BOILER (INCREASE HIGH FIRE DUTY CYCLE) | $158,000 | $725,000 | n/a |
UU0258 # 02 Y:2024 | 02 | 2024 | INSTALL / REPAIR INSULATION ON STEAM LINES | $25,800 | $6,200 | n/a |
UU0258 # 03 Y:2024 | 03 | 2024 | IMPROVE COMBUSTION CONTROL CAPABILITY | $12,600 | $54,500 | n/a |
UU0258 # 04 Y:2024 | 04 | 2024 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $1,690,000 | $23,500,000 | n/a |
UU0258 # 05 Y:2024 | 05 | 2024 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $7,890 | $11,500 | n/a |
UU0258 # 06 Y:2024 | 06 | 2024 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $2,570 | $5,140 | n/a |
UU0258 # 08 Y:2024 | 08 | 2024 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $180,000 | $20,000 | n/a |
UU0258 # 07 Y:2024 | 07 | 2024 | OPTIMIZE PLANT POWER FACTOR | $120,000 | $198,000 | n/a |
UU0259 # 05 Y:2024 | 05 | 2024 | STORE HEATED/ COOLED WATER FOR USE DURING PEAK DEMAND PERIODS | $53,643 | $33,000 | n/a |
UU0259 # 04 Y:2024 | 04 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $68,165 | $110,030 | n/a |
UU0259 # 06 Y:2024 | 06 | 2024 | INSTALL COMMON HEADER ON COMPRESSORS | $3,995 | $9,200 | n/a |
UU0259 # 01 Y:2024 | 01 | 2024 | USE WASTE HEAT WITH A CLOSED-CYCLE GAS TURBINE-GENERATOR SET TO COGENERATE ELECTRICITY AND HEAT | $3,866,540 | $17,885,484 | n/a |
UU0259 # 03 Y:2024 | 03 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $205,038 | $1,865,253 | n/a |