Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,298
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WI0325 # 05 Y:1998 | 05 | 1998 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $1,652 | $0 | Not Implemented |
WI0325 # 06 Y:1998 | 06 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $756 | $740 | Not Implemented |
WI0324 # 01 Y:1998 | 01 | 1998 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,936 | $0 | Not Implemented |
WI0324 # 02 Y:1998 | 02 | 1998 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $487 | $0 | Implemented |
WI0324 # 03 Y:1998 | 03 | 1998 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,780 | $850 | Not Implemented |
WI0324 # 04 Y:1998 | 04 | 1998 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,054 | $400 | Implemented |
WI0324 # 05 Y:1998 | 05 | 1998 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $381 | $90 | Implemented |
WI0324 # 06 Y:1998 | 06 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $372 | $640 | Implemented |
WI0324 # 07 Y:1998 | 07 | 1998 | REPLACE CLOTH RAGS WITH PAPER TOWELS | $1,039 | $0 | Not Implemented |
WI0323 # 01 Y:1998 | 01 | 1998 | TREAT AND REUSE RINSE WATERS | $6,555 | $1,475 | Not Implemented |
WI0323 # 02 Y:1998 | 02 | 1998 | SCHEDULE ROUTINE MAINTENANCE DURING NON-OPERATING PERIODS | $2,629 | $0 | Implemented |
WI0323 # 03 Y:1998 | 03 | 1998 | INSTALL TIMERS AND/OR THERMOSTATS | $2,343 | $600 | Not Implemented |
WI0323 # 04 Y:1998 | 04 | 1998 | PAY BILLS ON TIME TO AVOID LATE FEES | $820 | $0 | Implemented |
WI0323 # 05 Y:1998 | 05 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $183 | $468 | Not Implemented |
WI0322 # 01 Y:1998 | 01 | 1998 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $21,516 | $1,000 | Not Implemented |
WI0322 # 02 Y:1998 | 02 | 1998 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $11,052 | $500 | Not Implemented |
WI0322 # 03 Y:1998 | 03 | 1998 | INSTALL TIMERS AND/OR THERMOSTATS | $6,348 | $1,000 | Not Implemented |
WI0322 # 04 Y:1998 | 04 | 1998 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $4,205 | $4,500 | Not Implemented |
WI0322 # 05 Y:1998 | 05 | 1998 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $4,677 | $9,000 | Not Implemented |
WI0322 # 06 Y:1998 | 06 | 1998 | SHIFT FROM DAYTIME TO NIGHTTIME OPERATION | $3,817 | $0 | Not Implemented |
WI0322 # 07 Y:1998 | 07 | 1998 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,087 | $600 | Not Implemented |
WI0322 # 08 Y:1998 | 08 | 1998 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $2,376 | $0 | Not Implemented |
WI0322 # 09 Y:1998 | 09 | 1998 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $343 | $740 | Not Implemented |
WI0321 # 01 Y:1998 | 01 | 1998 | CLEAR AND RENT EXISTING SPACE | $159,400 | $5,292 | Implemented |
WI0321 # 02 Y:1998 | 02 | 1998 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $11,855 | $23,584 | Not Implemented |