Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,631
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0409 # 03 Y:1993 | 03 | 1993 | INSTALL TIMERS AND/OR THERMOSTATS | $1,251 | $450 | Implemented |
UD0408 # 01 Y:1993 | 01 | 1993 | INCREASE ELECTRICAL CONDUCTOR SIZE TO REDUCE DISTRIBUTION LOSSES | $2,008 | $1,500 | Implemented |
UD0408 # 02 Y:1993 | 02 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,052 | $21,676 | Implemented |
UD0408 # 03 Y:1993 | 03 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,726 | $0 | Implemented |
UD0408 # 04 Y:1993 | 04 | 1993 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $13,391 | $10,000 | Implemented |
UD0408 # 05 Y:1993 | 05 | 1993 | INSTALL TIMERS AND/OR THERMOSTATS | $6,067 | $3,000 | Implemented |
WV0010 # 01 Y:1993 | 01 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,499 | $1,000 | Implemented |
WV0010 # 06 Y:1993 | 06 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $201 | $5,827 | Implemented |
WV0010 # 07 Y:1993 | 07 | 1993 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $182 | $11,930 | Implemented |
WV0009 # 02 Y:1993 | 02 | 1993 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $153 | $194 | Implemented |
WV0009 # 05 Y:1993 | 05 | 1993 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,163 | $976 | Implemented |
WV0009 # 06 Y:1993 | 06 | 1993 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $425 | $295 | Implemented |
WV0009 # 07 Y:1993 | 07 | 1993 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $27,394 | $1,440 | Implemented |
UD0407 # 01 Y:1993 | 01 | 1993 | INCREASE ELECTRICAL CONDUCTOR SIZE TO REDUCE DISTRIBUTION LOSSES | $2,303 | $6,000 | Implemented |
UD0407 # 02 Y:1993 | 02 | 1993 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $4,300 | $1,000 | Implemented |
UD0407 # 03 Y:1993 | 03 | 1993 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $1,563 | $500 | Implemented |
UD0407 # 04 Y:1993 | 04 | 1993 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $2,346 | $1,500 | Implemented |
UD0406 # 01 Y:1993 | 01 | 1993 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $44,100 | $50,000 | Implemented |
UD0405 # 01 Y:1993 | 01 | 1993 | UPGRADE CONTROLS ON COMPRESSORS | $2,213 | $100 | Implemented |
UD0405 # 02 Y:1993 | 02 | 1993 | USE PROPERLY DESIGNED AND SIZED HVAC EQUIPMENT | $2,743 | $2,000 | Implemented |
UD0405 # 03 Y:1993 | 03 | 1993 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,176 | $2,511 | Implemented |
UD0405 # 04 Y:1993 | 04 | 1993 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $548 | $1,000 | Implemented |
UD0404 # 01 Y:1993 | 01 | 1993 | UPGRADE CONTROLS ON COMPRESSORS | $750 | $200 | Implemented |
UD0404 # 02 Y:1993 | 02 | 1993 | UPGRADE CONTROLS ON COMPRESSORS | $875 | $200 | Implemented |
UD0404 # 03 Y:1993 | 03 | 1993 | OPERATE BOILERS ON HIGH FIRE SETTING | $795 | $200 | Implemented |