Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,628
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0969 # 03 Y:2017 | 03 | 2017 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,188 | $30 | Implemented |
UD0969 # 05 Y:2017 | 05 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,419 | $1,000 | Implemented |
UD0969 # 06 Y:2017 | 06 | 2017 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $22,591 | $63,800 | Implemented |
UD0969 # 09 Y:2017 | 09 | 2017 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $3,251 | $30 | Implemented |
UD0969 # 11 Y:2017 | 11 | 2017 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,502 | $844 | Implemented |
UD0969 # 14 Y:2017 | 14 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,321 | $811 | Implemented |
UD0968 # 03 Y:2017 | 03 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,341 | $0 | Implemented |
UD0968 # 04 Y:2017 | 04 | 2017 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $4,217 | $118 | Implemented |
UD0968 # 05 Y:2017 | 05 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,870 | $0 | Implemented |
UD0968 # 13 Y:2017 | 13 | 2017 | USE OPTIMUM TEMPERATURE | $4,293 | $0 | Implemented |
UD0968 # 16 Y:2017 | 16 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $37,850 | $38,175 | Implemented |
UD0968 # 17 Y:2017 | 17 | 2017 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $27,353 | $42,400 | Implemented |
WV0546 # 01 Y:2017 | 01 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,125 | $26,267 | Implemented |
WV0546 # 03 Y:2017 | 03 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,180 | $11,575 | Implemented |
WV0546 # 04 Y:2017 | 04 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,920 | $4,595 | Implemented |
WV0546 # 06 Y:2017 | 06 | 2017 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $2,152 | $6,100 | Implemented |
WV0546 # 07 Y:2017 | 07 | 2017 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,898 | $0 | Implemented |
WV0546 # 08 Y:2017 | 08 | 2017 | DEVELOP A REPAIR/REPLACE POLICY | $1,672 | $600 | Implemented |
WV0546 # 09 Y:2017 | 09 | 2017 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $1,670 | $1,100 | Implemented |
WV0546 # 11 Y:2017 | 11 | 2017 | INSULATE BARE EQUIPMENT | $239 | $342 | Implemented |
WV0545 # 01 Y:2017 | 01 | 2017 | OPTIMIZE PLANT POWER FACTOR | $7,127 | $2,800 | Implemented |
WV0545 # 02 Y:2017 | 02 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,951 | $490 | Implemented |
WV0545 # 03 Y:2017 | 03 | 2017 | INSTALL SET-BACK TIMERS | $4,904 | $1,700 | Implemented |
WV0545 # 05 Y:2017 | 05 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,500 | $4,023 | Implemented |
WV0545 # 08 Y:2017 | 08 | 2017 | DEVELOP A REPAIR/REPLACE POLICY | $516 | $568 | Implemented |