Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,643
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0557 # 07 Y:2023 | 07 | 2023 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $46 | $294 | Implemented |
AS0557 # 05 Y:2023 | 05 | 2023 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $333 | $284 | Implemented |
AS0557 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,169 | $2,419 | Implemented |
AS0557 # 03 Y:2023 | 03 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $1,986 | $19,728 | Implemented |
AS0554 # 05 Y:2023 | 05 | 2023 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $2,680 | $600 | Implemented |
AS0554 # 04 Y:2023 | 04 | 2023 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $2,798 | $2,970 | Implemented |
AS0554 # 07 Y:2023 | 07 | 2023 | INSTALL OCCUPANCY SENSORS | $1,513 | $1,560 | Implemented |
AS0554 # 02 Y:2023 | 02 | 2023 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,520 | $2,832 | Implemented |
AS0554 # 01 Y:2023 | 01 | 2023 | USE SOLAR HEAT TO MAKE ELECTRICTY | $28,395 | $281,442 | Implemented |
AS0554 # 06 Y:2023 | 06 | 2023 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $1,609 | $1,858 | Implemented |
AS0554 # 08 Y:2023 | 08 | 2023 | USE PHOTOCELL CONTROLS | $805 | $1,700 | Implemented |
AS0554 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,704 | $6,059 | Implemented |
AS0552 # 05 Y:2023 | 05 | 2023 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $357 | $10,234 | Implemented |
AS0551 # 04 Y:2023 | 04 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $784 | $3,277 | Implemented |
AS0549 # 03 Y:2023 | 03 | 2023 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $3,340 | $6,151 | Implemented |
AS0551 # 01 Y:2023 | 01 | 2023 | USE FLOW CONTROL VALVES ON EQUIPMENT TO OPTIMIZE WATER USE | $2,434 | $2,202 | Implemented |
AS0549 # 05 Y:2023 | 05 | 2023 | INSTALL TIMERS AND/OR THERMOSTATS | $328 | $540 | Implemented |
AS0550 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $152 | $109 | Implemented |
AS0549 # 02 Y:2023 | 02 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,226 | $17,834 | Implemented |
AS0549 # 01 Y:2023 | 01 | 2023 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $41,664 | $123,750 | Implemented |
AS0552 # 06 Y:2023 | 06 | 2023 | SHADE WINDOWS FROM SUMMER SUN | $281 | $550 | Implemented |
AS0550 # 02 Y:2023 | 02 | 2023 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $2,005 | $6,140 | Implemented |
AS0551 # 05 Y:2023 | 05 | 2023 | USE PHOTOCELL CONTROLS | $378 | $819 | Implemented |
AS0551 # 03 Y:2023 | 03 | 2023 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $1,477 | $3,284 | Implemented |
AS0551 # 02 Y:2023 | 02 | 2023 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $1,528 | $7,174 | Implemented |