Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,539
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
LE0389 # 01 Y:2015 | 01 | 2015 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $1,935 | $450 | Implemented |
LE0389 # 02 Y:2015 | 02 | 2015 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $8,547 | $4,500 | Implemented |
LE0389 # 03 Y:2015 | 03 | 2015 | REPLACE CITY WATER WITH RECYCLED WATER VIA COOLING TOWER | $21,418 | $21,650 | Implemented |
LE0389 # 04 Y:2015 | 04 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $642 | $1,000 | Implemented |
LE0389 # 05 Y:2015 | 05 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,458 | $81,373 | Implemented |
LE0390 # 06 Y:2015 | 06 | 2015 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $47,479 | $25,500 | Implemented |
LE0386 # 01 Y:2014 | 01 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $8,661 | $32 | Implemented |
LE0386 # 02 Y:2014 | 02 | 2014 | REPAIR AND ELIMINATE STEAM LEAKS | $61,300 | $2,592 | Implemented |
LE0386 # 03 Y:2014 | 03 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,910 | $1,000 | Implemented |
LE0386 # 04 Y:2014 | 04 | 2014 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $43,975 | $10,000 | Implemented |
LE0386 # 06 Y:2014 | 06 | 2014 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $12,502 | $16,700 | Implemented |
LE0386 # 09 Y:2014 | 09 | 2014 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $757 | $2,250 | Implemented |
LE0384 # 02 Y:2014 | 02 | 2014 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,272 | $1,481 | Implemented |
LE0384 # 06 Y:2014 | 06 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,875 | $3,304 | Implemented |
LE0384 # 07 Y:2014 | 07 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,620 | $12,950 | Implemented |
LE0384 # 08 Y:2014 | 08 | 2014 | INSTALL TIMERS AND/OR THERMOSTATS | $3,342 | $234 | Implemented |
LE0384 # 09 Y:2014 | 09 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,397 | $30,000 | Implemented |
LE0384 # 10 Y:2014 | 10 | 2014 | REPLACE BROKEN WINDOWS AND/OR WINDOW SASH | $7,346 | $551,550 | Implemented |
LE0383 # 01 Y:2014 | 01 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,489 | $40 | Implemented |
LE0383 # 02 Y:2014 | 02 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $4,539 | $300 | Implemented |
WV0492 # 01 Y:2014 | 01 | 2014 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $8,061 | $1,700 | Implemented |
WV0492 # 02 Y:2014 | 02 | 2014 | COVER OPEN TANKS | $7,268 | $1,145 | Implemented |
WV0492 # 05 Y:2014 | 05 | 2014 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,126 | $3,000 | Implemented |
WV0492 # 06 Y:2014 | 06 | 2014 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,774 | $8,160 | Implemented |
WV0492 # 07 Y:2014 | 07 | 2014 | ESTABLISH A PREDICTIVE MAINTENANCE PROGRAM | $1,914 | $1,000 | Implemented |