Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,732
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0404 # 04 Y:2001 | 04 | 2001 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $859 | $2,400 | Implemented |
OR0404 # 05 Y:2001 | 05 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $448 | $500 | Implemented |
OR0402 # 01 Y:2001 | 01 | 2001 | UPGRADE OBSOLETE EQUIPMENT | $53,000 | $45,000 | Implemented |
OR0402 # 02 Y:2001 | 02 | 2001 | TRAIN OPERATORS FOR MAXIMUM OPERATING EFFICIENCY | $6,880 | $1,230 | Implemented |
OR0394 # 01 Y:2001 | 01 | 2001 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $31,896 | $31,163 | Implemented |
OR0394 # 02 Y:2001 | 02 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,492 | $5,000 | Implemented |
OR0394 # 04 Y:2001 | 04 | 2001 | USE PHOTOCELL CONTROLS | $1,883 | $2,150 | Implemented |
OR0394 # 05 Y:2001 | 05 | 2001 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $11,074 | $29,915 | Implemented |
OR0391 # 01 Y:2001 | 01 | 2001 | OPTIMIZE PRODUCTION LOT SIZES AND INVENTORIES | $324,000 | $79,300 | Implemented |
OR0391 # 02 Y:2001 | 02 | 2001 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $2,300 | $0 | Implemented |
OR0389 # 01 Y:2001 | 01 | 2001 | MODIFY CURRENT INCENTIVE PROGRAM | $289,800 | $26,680 | Implemented |
OR0389 # 02 Y:2001 | 02 | 2001 | CHANGE METHOD OF DEIONIZED WATER PRODUCTION | $29,980 | $20,000 | Implemented |
OR0389 # 03 Y:2001 | 03 | 2001 | USE MOST EFFICIENT EQUIPMENT AT IT'S MAXIMUM CAPACITY AND LESS EFFICIENT EQUIPMENT ONLY WHEN NECESSARY | $6,790 | $4,721 | Implemented |
OR0389 # 04 Y:2001 | 04 | 2001 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $5,384 | $3,000 | Implemented |
OR0389 # 05 Y:2001 | 05 | 2001 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,103 | $590 | Implemented |
OR0388 # 01 Y:2001 | 01 | 2001 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $187,500 | $18,000 | Implemented |
OR0388 # 02 Y:2001 | 02 | 2001 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $290,325 | $250,000 | Implemented |
OR0388 # 03 Y:2001 | 03 | 2001 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $108,900 | $60,000 | Implemented |
OR0388 # 04 Y:2001 | 04 | 2001 | MODIFY CURRENT INCENTIVE PROGRAM | $368,300 | $29,120 | Implemented |
OR0387 # 01 Y:2001 | 01 | 2001 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $176,000 | $5,000 | Implemented |
OR0387 # 02 Y:2001 | 02 | 2001 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $440,800 | $128,700 | Implemented |
OR0387 # 05 Y:2001 | 05 | 2001 | OPTIMIZE LOT SIZES TO REDUCE INVENTORY CARRYING COSTS | $57,000 | $74,000 | Implemented |
OR0387 # 06 Y:2001 | 06 | 2001 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $12,800 | $5,850 | Implemented |
OR0387 # 08 Y:2001 | 08 | 2001 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $1,885 | $300 | Implemented |
OR0387 # 09 Y:2001 | 09 | 2001 | REUSE / RECYCLE/ SELL RUBBER PRODUCTS | $2,320 | $0 | Implemented |