Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,486
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0507 # 06 Y:2017 | 06 | 2017 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $5,369 | $12,526 | Implemented |
SF0507 # 07 Y:2017 | 07 | 2017 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $54,833 | $312,470 | Implemented |
SF0506 # 01 Y:2017 | 01 | 2017 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $2,307 | $0 | Implemented |
SF0506 # 02 Y:2017 | 02 | 2017 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $7,881 | $728 | Implemented |
SF0506 # 03 Y:2017 | 03 | 2017 | TURN OFF EQUIPMENT WHEN NOT IN USE | $4,033 | $4,499 | Implemented |
SF0506 # 05 Y:2017 | 05 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $19,722 | $46,373 | Implemented |
SD0554 # 01 Y:2017 | 01 | 2017 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $30,343 | $65,600 | Implemented |
SD0554 # 03 Y:2017 | 03 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,421 | $15,275 | Implemented |
SD0554 # 05 Y:2017 | 05 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $356 | $1,450 | Implemented |
SD0554 # 06 Y:2017 | 06 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $274 | $1,300 | Implemented |
SD0554 # 07 Y:2017 | 07 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $271 | $200 | Implemented |
SF0505 # 07 Y:2017 | 07 | 2017 | INSULATE BARE EQUIPMENT | $3,828 | $5,423 | Implemented |
SF0505 # 08 Y:2017 | 08 | 2017 | INSULATE BARE EQUIPMENT | $1,069 | $1,882 | Implemented |
SD0553 # 02 Y:2017 | 02 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $24,252 | $39,079 | Implemented |
SD0553 # 03 Y:2017 | 03 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $17,203 | $59,750 | Implemented |
SD0553 # 06 Y:2017 | 06 | 2017 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,930 | $7,400 | Implemented |
SD0553 # 08 Y:2017 | 08 | 2017 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $3,656 | $3,225 | Implemented |
SF0503 # 01 Y:2017 | 01 | 2017 | USE OUTSIDE COLD WATER SOURCE AS A SUPPLY OF COOLING WATER | $8,497 | $7,120 | Implemented |
SF0503 # 02 Y:2017 | 02 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $123,711 | $243,952 | Implemented |
SF0503 # 03 Y:2017 | 03 | 2017 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $802,468 | $1,600,000 | Implemented |
SF0503 # 04 Y:2017 | 04 | 2017 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $38,530 | $102,500 | Implemented |
SF0503 # 05 Y:2017 | 05 | 2017 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $3,829 | $29,980 | Implemented |
SF0504 # 01 Y:2017 | 01 | 2017 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,032 | $100 | Implemented |
SF0504 # 03 Y:2017 | 03 | 2017 | INSTALL OCCUPANCY SENSORS | $1,736 | $7,335 | Implemented |
SD0551 # 02 Y:2017 | 02 | 2017 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,959 | $35,776 | Implemented |