IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

3,191

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
BD0309 # 04 Y:2006 04 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $809 $1,000 Implemented
BD0309 # 05 Y:2006 05 2006 RECOVER WASTE HEAT FROM EQUIPMENT $7,023 $1,880 Implemented
BD0309 # 06 Y:2006 06 2006 INSTALL OCCUPANCY SENSORS $653 $1,200 Implemented
BD0309 # 07 Y:2006 07 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $309 $475 Implemented
IC0114 # 03 Y:2006 03 2006 MINIMIZE BOILER BLOWDOWN WITH BETTER FEEDWATER TREATMENT $19,000 $63,000 Implemented
IC0114 # 09 Y:2006 09 2006 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $10,414 $65,273 Implemented
IC0114 # 10 Y:2006 10 2006 USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER $2,000 $8,400 Implemented
IC0114 # 11 Y:2006 11 2006 INSTALL / REPAIR INSULATION ON STEAM LINES $4,400 $1,200 Implemented
IC0114 # 12 Y:2006 12 2006 REPAIR AND ELIMINATE STEAM LEAKS $2,000 $2,800 Implemented
IC0114 # 13 Y:2006 13 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,383 $9,400 Implemented
BD0301 # 01 Y:2006 01 2006 USE RADIANT HEATER FOR SPOT HEATING $94,570 $91,000 Implemented
BD0301 # 02 Y:2006 02 2006 RECOVER WASTE HEAT FROM EQUIPMENT $43,599 $22,780 Implemented
BD0301 # 03 Y:2006 03 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,786 $1,800 Implemented
BD0301 # 04 Y:2006 04 2006 USE PHOTOCELL CONTROLS $1,759 $1,750 Implemented
BD0301 # 05 Y:2006 05 2006 RECOVER WASTE HEAT FROM EQUIPMENT $1,640 $500 Implemented
BD0301 # 07 Y:2006 07 2006 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $763 $500 Implemented
BD0301 # 08 Y:2006 08 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $342 $350 Implemented
BD0301 # 10 Y:2006 10 2006 AUTOMATE FINISHING PROCESS $1,669,200 $285,000 Implemented
BD0301 # 11 Y:2006 11 2006 PAY BILLS ON TIME TO AVOID LATE FEES $995 $0 Implemented
IC0113 # 02 Y:2006 02 2006 TURN OFF EQUIPMENT WHEN NOT IN USE $10,036 $0 Implemented
IC0113 # 03 Y:2006 03 2006 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $15,683 $66,529 Implemented
IC0113 # 04 Y:2006 04 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $1,398 $8,517 Implemented
IC0113 # 05 Y:2006 05 2006 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $2,840 $900 Implemented
BD0303 # 03 Y:2006 03 2006 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $2,511 $1,500 Implemented
BD0303 # 04 Y:2006 04 2006 RECOVER WASTE HEAT FROM EQUIPMENT $2,403 $400 Implemented