Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
407
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0598 # 02 Y:2006 | 02 | 2006 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $19,748 | $1,125 | Implemented |
MA0582 # 10 Y:2005 | 10 | 2005 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $1,584 | $1,300 | Implemented |
MA0582 # 09 Y:2005 | 09 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,540 | $800 | Implemented |
MA0582 # 08 Y:2005 | 08 | 2005 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $6,340 | $25,150 | Implemented |
MA0582 # 07 Y:2005 | 07 | 2005 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,815 | $7,660 | Implemented |
MA0582 # 06 Y:2005 | 06 | 2005 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $7,599 | $2,010 | Implemented |
MA0582 # 04 Y:2005 | 04 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $14,153 | $0 | Implemented |
MA0582 # 03 Y:2005 | 03 | 2005 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $15,630 | $6,540 | Implemented |
MA0582 # 02 Y:2005 | 02 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $37,163 | $86,315 | Implemented |
MA0581 # 11 Y:2005 | 11 | 2005 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $3,467 | $8,300 | Implemented |
MA0581 # 10 Y:2005 | 10 | 2005 | ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF | $5,166 | $3,100 | Implemented |
MA0581 # 09 Y:2005 | 09 | 2005 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $9,508 | $160 | Implemented |
MA0581 # 08 Y:2005 | 08 | 2005 | RECOVER WASTE HEAT FROM EQUIPMENT | $10,675 | $4,675 | Implemented |
MA0581 # 07 Y:2005 | 07 | 2005 | ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF | $10,812 | $5,328 | Implemented |
MA0581 # 04 Y:2005 | 04 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $30,652 | $18,550 | Implemented |
MA0581 # 02 Y:2005 | 02 | 2005 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $81,700 | $18,200 | Implemented |
MA0579 # 08 Y:2005 | 08 | 2005 | INSULATE BARE EQUIPMENT | $647 | $1,170 | Implemented |
MA0579 # 06 Y:2005 | 06 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,484 | $450 | Implemented |
MA0579 # 05 Y:2005 | 05 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $3,427 | $7,389 | Implemented |
MA0579 # 04 Y:2005 | 04 | 2005 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $3,893 | $4,197 | Implemented |
MA0579 # 01 Y:2005 | 01 | 2005 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $8,816 | $7,000 | Implemented |
MA0578 # 06 Y:2005 | 06 | 2005 | IMPROVE COMBUSTION CONTROL CAPABILITY | $36,304 | $600 | Implemented |
MA0578 # 05 Y:2005 | 05 | 2005 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $1,718 | $5,475 | Implemented |
MA0578 # 03 Y:2005 | 03 | 2005 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $4,767 | $25,000 | Implemented |
MA0578 # 01 Y:2005 | 01 | 2005 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $86,353 | $20,000 | Implemented |