Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,532
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
WV0345 # 12 Y:2006 | 12 | 2006 | DEVELOP A REPAIR/REPLACE POLICY | $5,468 | $800 | Implemented |
LE0237 # 03 Y:2006 | 03 | 2006 | USE CLOSED CYCLE PROCESS TO MINIMIZE WASTE WATER PRODUCTION | $64,774 | $2,000 | Implemented |
LE0237 # 04 Y:2006 | 04 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,057 | $1,000 | Implemented |
LE0237 # 07 Y:2006 | 07 | 2006 | INSTALL OCCUPANCY SENSORS | $3,162 | $900 | Implemented |
LE0236 # 05 Y:2006 | 05 | 2006 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $15,083 | $2,500 | Implemented |
LE0235 # 02 Y:2006 | 02 | 2006 | PREHEAT COMBUSTION AIR WITH WASTE HEAT | $202,503 | $95,000 | Implemented |
LE0235 # 03 Y:2006 | 03 | 2006 | UPGRADE OBSOLETE EQUIPMENT | $192,971 | $250,000 | Implemented |
LE0235 # 05 Y:2006 | 05 | 2006 | ADJUST BURNERS FOR EFFICIENT OPERATION | $66,844 | $100 | Implemented |
LE0235 # 06 Y:2006 | 06 | 2006 | ADJUST BURNERS FOR EFFICIENT OPERATION | $63,349 | $20,000 | Implemented |
LE0235 # 07 Y:2006 | 07 | 2006 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $22,786 | $30,000 | Implemented |
LE0235 # 09 Y:2006 | 09 | 2006 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $12,444 | $6,000 | Implemented |
LE0235 # 11 Y:2006 | 11 | 2006 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $9,908 | $7,500 | Implemented |
LE0235 # 12 Y:2006 | 12 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,006 | $1,000 | Implemented |
LE0233 # 04 Y:2006 | 04 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,332 | $800 | Implemented |
LE0233 # 10 Y:2006 | 10 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,514 | $12,000 | Implemented |
LE0231 # 03 Y:2006 | 03 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $29,942 | $13,500 | Implemented |
LE0231 # 04 Y:2006 | 04 | 2006 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $26,565 | $51,000 | Implemented |
LE0231 # 05 Y:2006 | 05 | 2006 | REPAIR OR REPLACE STEAM TRAPS | $21,498 | $4,500 | Implemented |
LE0231 # 06 Y:2006 | 06 | 2006 | INSTALL PARTITIONS TO REDUCE SIZE OF CONDITIONED SPACE | $17,212 | $12,500 | Implemented |
LE0231 # 08 Y:2006 | 08 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $13,127 | $400 | Implemented |
LE0231 # 09 Y:2006 | 09 | 2006 | IMPROVE COMBUSTION CONTROL CAPABILITY | $7,881 | $2,500 | Implemented |
LE0231 # 10 Y:2006 | 10 | 2006 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $2,915 | $189 | Implemented |
LE0231 # 11 Y:2006 | 11 | 2006 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,485 | $3,600 | Implemented |
LE0229 # 02 Y:2006 | 02 | 2006 | REPLACE FOSSIL FUEL EQUIPMENT WITH ELECTRICAL EQUIPMENT | $64,670 | $27,200 | Implemented |
LE0229 # 03 Y:2006 | 03 | 2006 | RECYCLE WASTE INK AND CLEANUP SOLVENT | $36,000 | $50,000 | Implemented |