Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,882
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
KU0131 # 03 Y:1984 | 03 | 1984 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,281 | $200 | Implemented |
KU0131 # 05 Y:1984 | 05 | 1984 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,310 | $170 | Implemented |
KU0131 # 07 Y:1984 | 07 | 1984 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $485 | $350 | Implemented |
KU0131 # 13 Y:1984 | 13 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $396 | $0 | Implemented |
KU0131 # 14 Y:1984 | 14 | 1984 | ESTABLISH EQUIPMENT MAINTENANCE SCHEDULE | $330 | $0 | Implemented |
KU0131 # 16 Y:1984 | 16 | 1984 | SHUT OFF PILOTS IN STANDBY EQUIPMENT | $136 | $0 | Implemented |
KU0131 # 19 Y:1984 | 19 | 1984 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $113 | $39 | Implemented |
KU0132 # 01 Y:1984 | 01 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,142 | $6,807 | Implemented |
KU0132 # 02 Y:1984 | 02 | 1984 | IMPROVE LUBRICATION PRACTICES | $3,765 | $800 | Implemented |
KU0132 # 03 Y:1984 | 03 | 1984 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $3,978 | $3,155 | Implemented |
KU0132 # 05 Y:1984 | 05 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $903 | $0 | Implemented |
KU0132 # 08 Y:1984 | 08 | 1984 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,443 | $85 | Implemented |
KU0132 # 09 Y:1984 | 09 | 1984 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $1,418 | $1,110 | Implemented |
KU0132 # 12 Y:1984 | 12 | 1984 | REDUCE HOT WATER TEMPERATURE TO THE MINIMUM REQUIRED | $954 | $0 | Implemented |
KU0132 # 13 Y:1984 | 13 | 1984 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $662 | $0 | Implemented |
KU0132 # 14 Y:1984 | 14 | 1984 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $367 | $800 | Implemented |
KU0133 # 01 Y:1984 | 01 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,390 | $10,201 | Implemented |
KU0133 # 02 Y:1984 | 02 | 1984 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $870 | $1,810 | Implemented |
KU0133 # 03 Y:1984 | 03 | 1984 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $10,922 | $7,500 | Implemented |
KU0133 # 05 Y:1984 | 05 | 1984 | USE PROPER THICKNESS OF INSULATION ON BUILDING ENVELOPE | $5,567 | $1,589 | Implemented |
KU0133 # 06 Y:1984 | 06 | 1984 | USE ONLY AMOUNT OF AIR NECESSARY TO PREVENT EXPLOSION HAZARD | $4,813 | $2,800 | Implemented |
KU0133 # 08 Y:1984 | 08 | 1984 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,626 | $0 | Implemented |
KU0133 # 09 Y:1984 | 09 | 1984 | INSTALL AUTOMATIC STACK DAMPER | $1,231 | $3,300 | Implemented |
KU0133 # 10 Y:1984 | 10 | 1984 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,584 | $2,900 | Implemented |
KU0133 # 11 Y:1984 | 11 | 1984 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $1,316 | $450 | Implemented |