Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,265
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AM0456 # 05 Y:2004 | 05 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,870 | $400 | Implemented |
AM0456 # 06 Y:2004 | 06 | 2004 | REPAIR AND ELIMINATE STEAM LEAKS | $1,100 | $4,950 | Implemented |
AM0455 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $680 | $1,500 | Implemented |
AM0455 # 05 Y:2004 | 05 | 2004 | COMBINE UTILITY METERS | $528 | $0 | Implemented |
AM0455 # 06 Y:2004 | 06 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $200 | $0 | Implemented |
AM0455 # 07 Y:2004 | 07 | 2004 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $120 | $74 | Implemented |
TA0070 # 01 Y:2004 | 01 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $43,350 | $0 | Implemented |
TA0070 # 02 Y:2004 | 02 | 2004 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $21,150 | $-21,150 | Implemented |
TA0070 # 03 Y:2004 | 03 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $7,300 | $0 | Implemented |
TA0070 # 05 Y:2004 | 05 | 2004 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $2,990 | $130 | Implemented |
TA0070 # 06 Y:2004 | 06 | 2004 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $2,650 | $0 | Implemented |
TA0070 # 08 Y:2004 | 08 | 2004 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $2,020 | $410 | Implemented |
TA0070 # 09 Y:2004 | 09 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,885 | $50 | Implemented |
TA0070 # 11 Y:2004 | 11 | 2004 | INSTALL OCCUPANCY SENSORS | $680 | $290 | Implemented |
AM0453 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,040 | $500 | Implemented |
AM0453 # 04 Y:2004 | 04 | 2004 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $660 | $0 | Implemented |
AM0453 # 05 Y:2004 | 05 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $370 | $250 | Implemented |
TA0069 # 01 Y:2004 | 01 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $9,482 | $0 | Implemented |
TA0069 # 02 Y:2004 | 02 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,293 | $9,519 | Implemented |
TA0069 # 03 Y:2004 | 03 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,975 | $10,974 | Implemented |
TA0069 # 04 Y:2004 | 04 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $800 | $316 | Implemented |
TA0069 # 07 Y:2004 | 07 | 2004 | INSTALL OCCUPANCY SENSORS | $371 | $284 | Implemented |
TA0069 # 08 Y:2004 | 08 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $351 | $542 | Implemented |
TA0068 # 01 Y:2004 | 01 | 2004 | REDUCE SCRAP PRODUCTION | $400,000 | $8,000 | Implemented |
TA0068 # 02 Y:2004 | 02 | 2004 | MODIFY PROCESS TO REDUCE MATERIAL USE/COST | $82,002 | $12,000 | Implemented |