Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,400
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0974 # 07 Y:2024 | 07 | 2024 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,466 | $6,640 | Implemented |
GT0974 # 08 Y:2024 | 08 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,751 | $3,150 | Implemented |
GT0974 # 06 Y:2024 | 06 | 2024 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,067 | $2,139 | Implemented |
GT0974 # 04 Y:2024 | 04 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,774 | $1,850 | Implemented |
GT0974 # 01 Y:2024 | 01 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,361 | $200 | Implemented |
GT0974 # 05 Y:2024 | 05 | 2024 | TURN OFF EQUIPMENT WHEN NOT IN USE | $5,870 | $2,400 | Implemented |
GT0973 # 02 Y:2024 | 02 | 2024 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $394 | $90 | Implemented |
GT0973 # 01 Y:2024 | 01 | 2024 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $7,645 | $800 | Implemented |
GT0973 # 05 Y:2024 | 05 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,586 | $1,850 | Implemented |
GT0973 # 04 Y:2024 | 04 | 2024 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $305 | $200 | Implemented |
GT0972 # 03 Y:2024 | 03 | 2024 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $1,730 | $400 | Implemented |
GT0972 # 01 Y:2024 | 01 | 2024 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $17,131 | $1,850 | Implemented |
GT0969 # 02 Y:2023 | 02 | 2023 | APPLY FOR TAX-FREE STATUS FOR ENERGY PURCHASES | $15,032 | $800 | Implemented |
GT0969 # 07 Y:2023 | 07 | 2023 | PAY UTILITY BILLS ON TIME | $419 | $200 | Implemented |
GT0969 # 05 Y:2023 | 05 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $4,944 | $1,950 | Implemented |
GT0969 # 04 Y:2023 | 04 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,439 | $1,850 | Implemented |
GT0969 # 01 Y:2023 | 01 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $8,386 | $100 | Implemented |
GT0969 # 03 Y:2023 | 03 | 2023 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $929 | $200 | Implemented |
GT0969 # 09 Y:2023 | 09 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $31,558 | $49,875 | Implemented |
GT0969 # 08 Y:2023 | 08 | 2023 | CONSERVE ENERGY BY EFFICIENT USE OF VENDING MACHINES | $389 | $270 | Implemented |
GT0968 # 03 Y:2023 | 03 | 2023 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $73,640 | $23,680 | Implemented |
GT0968 # 02 Y:2023 | 02 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $104,725 | $13,000 | Implemented |
GT0968 # 01 Y:2023 | 01 | 2023 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $64,657 | $1,850 | Implemented |
GT0968 # 04 Y:2023 | 04 | 2023 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,052 | $3,250 | Implemented |
GT0967 # 03 Y:2023 | 03 | 2023 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $4,800 | $1,000 | Implemented |