Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
100
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
IA0187 # 08 Y:1997 | 08 | 1997 | CONVERT TO ELECTROSTATIC POWDER COATING | $12,006 | $7,800 | Implemented |
IA0187 # 06 Y:1997 | 06 | 1997 | INSTALL TIMERS AND/OR THERMOSTATS | $361 | $384 | Implemented |
IA0187 # 01 Y:1997 | 01 | 1997 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,822 | $1,825 | Implemented |
IA0187 # 04 Y:1997 | 04 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $396 | $922 | Implemented |
IA0187 # 09 Y:1997 | 09 | 1997 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $3,368 | $1,054 | Implemented |
IA0187 # 07 Y:1997 | 07 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $140 | $170 | Implemented |
IA0182 # 03 Y:1997 | 03 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $159 | $284 | Implemented |
IA0182 # 07 Y:1997 | 07 | 1997 | $5,140 | $5,880 | Implemented | |
IA0182 # 02 Y:1997 | 02 | 1997 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,806 | $2,000 | Implemented |
IA0182 # 05 Y:1997 | 05 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $113 | $106 | Implemented |
IA0181 # 07 Y:1997 | 07 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $885 | $200 | Implemented |
IA0181 # 05 Y:1997 | 05 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $420 | $950 | Implemented |
IA0181 # 02 Y:1997 | 02 | 1997 | CHANGE PROCEDURES / EQUIPMENT / OPERATING CONDITIONS | $41,865 | $50,000 | Implemented |
IA0181 # 03 Y:1997 | 03 | 1997 | PURCHASE GAS DIRECTLY FROM A CONTRACT GAS SUPPLIER | $31,001 | $4,200 | Implemented |
IA0185 # 02 Y:1997 | 02 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $6,613 | $1,280 | Implemented |
IA0185 # 03 Y:1997 | 03 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,249 | $422 | Implemented |
IA0185 # 04 Y:1997 | 04 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $514 | $1,058 | Implemented |
IA0179 # 04 Y:1997 | 04 | 1997 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,599 | $1,019 | Implemented |
IA0179 # 02 Y:1997 | 02 | 1997 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $2,253 | $2,697 | Implemented |
IA0179 # 03 Y:1997 | 03 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,789 | $1,842 | Implemented |
IA0179 # 07 Y:1997 | 07 | 1997 | INSTALL OCCUPANCY SENSORS | $167 | $166 | Implemented |
DS0100 # 03 Y:1997 | 03 | 1997 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $3,757 | $775 | Implemented |
DS0100 # 01 Y:1997 | 01 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,501 | $7,978 | Implemented |
DS0100 # 02 Y:1997 | 02 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $961 | $1,250 | Implemented |
DS0099 # 04 Y:1997 | 04 | 1997 | METER RECYCLED WATER (TO REDUCE SEWER CHARGES) | $1,231 | $700 | Implemented |