Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
1,100
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0601 # 01 Y:2025 | 01 | 2025 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $130,000 | $66,000 | n/a |
AS0601 # 02 Y:2025 | 02 | 2025 | RECOVER AND REUSE WASTE MATERIAL | $76,561 | $120,000 | n/a |
AS0601 # 03 Y:2025 | 03 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $21,962 | $176,288 | n/a |
AS0601 # 04 Y:2025 | 04 | 2025 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $4,347 | $618 | n/a |
AS0601 # 05 Y:2025 | 05 | 2025 | INSULATE BARE EQUIPMENT | $852 | $3,546 | n/a |
AS0601 # 06 Y:2025 | 06 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $416 | $942 | n/a |
AS0601 # 07 Y:2025 | 07 | 2025 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $105 | $180 | n/a |
OK1136 # 01 Y:2025 | 01 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,211 | $2,580 | n/a |
OK1136 # 02 Y:2025 | 02 | 2025 | USE SOLAR HEAT TO MAKE ELECTRICTY | $7,297 | $87,210 | n/a |
OK1136 # 03 Y:2025 | 03 | 2025 | CLEAN AND MAINTAIN REFRIGERANT CONDENSERS AND TOWERS | $2,165 | $1,424 | n/a |
OK1136 # 04 Y:2025 | 04 | 2025 | TURN OFF EQUIPMENT WHEN NOT IN USE | $7,441 | $0 | n/a |
LS2510 # 01 Y:2025 | 01 | 2025 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $4,765 | $200 | n/a |
LS2510 # 02 Y:2025 | 02 | 2025 | INSTALL TIMERS AND/OR THERMOSTATS | $287 | $50 | n/a |
LS2510 # 03 Y:2025 | 03 | 2025 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,945 | $450 | n/a |
LS2510 # 04 Y:2025 | 04 | 2025 | USE IN-PROCESS RECYCLING WHENEVER POSSIBLE | $24,480 | $14,000 | n/a |
LS2510 # 05 Y:2025 | 05 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $28,682 | $21,000 | n/a |
LS2510 # 06 Y:2025 | 06 | 2025 | ADJUST BURNERS FOR EFFICIENT OPERATION | $62,919 | $100,000 | n/a |
LS2510 # 07 Y:2025 | 07 | 2025 | ENHANCE SENSITIVITY OF TEMPERATURE CONTROL AND CUTOFF | $2,760 | $4,900 | n/a |
LS2510 # 08 Y:2025 | 08 | 2025 | REPLACE BOILER | $14,158 | $66,000 | n/a |
NL0107 # 01 Y:2025 | 01 | 2025 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $23,651 | $66,700 | n/a |
NL0107 # 02 Y:2025 | 02 | 2025 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $21,036 | $165,000 | n/a |
NL0107 # 03 Y:2025 | 03 | 2025 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $1,532 | $2,280 | n/a |
NL0107 # 04 Y:2025 | 04 | 2025 | CLOSE HOLES AND OPENINGS IN BUILDING SUCH AS BROKEN WINDOWS | $109 | $30 | n/a |
AS0599 # 01 Y:2025 | 01 | 2025 | BURN A LESS EXPENSIVE GRADE OF FUEL | $625,275 | $321,478 | n/a |
AS0599 # 02 Y:2025 | 02 | 2025 | REDESIGN PROCESS | $778,933 | $500,000 | n/a |