Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
12,007
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0472 # 02 Y:2015 | 02 | 2015 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,897 | $6,325 | Implemented |
SF0472 # 03 Y:2015 | 03 | 2015 | INSTALL OCCUPANCY SENSORS | $1,873 | $4,287 | Implemented |
SF0472 # 04 Y:2015 | 04 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,003 | $19,142 | Implemented |
SF0472 # 05 Y:2015 | 05 | 2015 | USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES | $4,245 | $18,586 | Not Implemented |
SD0516 # 01 Y:2015 | 01 | 2015 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $21,830 | $48,900 | Implemented |
SD0516 # 02 Y:2015 | 02 | 2015 | REDUCE SPACE CONDITIONING DURING NON-WORKING HOURS | $12,584 | $3,900 | Implemented |
SD0516 # 03 Y:2015 | 03 | 2015 | INSTALL OCCUPANCY SENSORS | $2,406 | $2,370 | Not Implemented |
SD0516 # 04 Y:2015 | 04 | 2015 | USE PHOTOCELL CONTROLS | $1,539 | $1,295 | Implemented |
SD0516 # 05 Y:2015 | 05 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,238 | $200 | Implemented |
SD0516 # 06 Y:2015 | 06 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $797 | $1,500 | Implemented |
SD0514 # 01 Y:2015 | 01 | 2015 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $188,380 | $121,434 | Implemented |
SD0514 # 02 Y:2015 | 02 | 2015 | REDUCE TEMPERATURE OF PROCESS EQUIPMENT WHEN ON STANDBY | $34,024 | $1,200 | Implemented |
SD0514 # 03 Y:2015 | 03 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,935 | $2,000 | Implemented |
SD0514 # 04 Y:2015 | 04 | 2015 | INSTALL OCCUPANCY SENSORS | $2,376 | $3,380 | Implemented |
SD0514 # 05 Y:2015 | 05 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,336 | $400 | Not Implemented |
SF0471 # 01 Y:2015 | 01 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,634 | $0 | Not Implemented |
SF0471 # 02 Y:2015 | 02 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $554 | $134 | Implemented |
SF0471 # 03 Y:2015 | 03 | 2015 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $17,492 | $23,804 | Not Implemented |
SF0471 # 04 Y:2015 | 04 | 2015 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $25,853 | $50,144 | Not Implemented |
SF0470 # 01 Y:2015 | 01 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $10,220 | $4,488 | Implemented |
SF0470 # 02 Y:2015 | 02 | 2015 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $5,421 | $3,541 | Implemented |
SF0470 # 03 Y:2015 | 03 | 2015 | INCREASE AMOUNT OF CONDENSATE RETURNED | $26,563 | $30,811 | Implemented |
SF0470 # 04 Y:2015 | 04 | 2015 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $5,546 | $11,844 | Implemented |
SF0470 # 05 Y:2015 | 05 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,206 | $17,797 | Implemented |
SF0470 # 06 Y:2015 | 06 | 2015 | USE SOLAR HEAT TO MAKE ELECTRICTY | $91,176 | $450,224 | Implemented |