Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
11,865
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0462 # 03 Y:2015 | 03 | 2015 | RECHARGE BATTERIES ON DURING OFF-PEAK DEMAND PERIODS | $1,475 | $793 | Implemented |
SF0462 # 04 Y:2015 | 04 | 2015 | USE INSULATION IN FURNACES TO FACILITATE HEATING / COOLING | $2,104 | $1,941 | Implemented |
SD0496 # 01 Y:2015 | 01 | 2015 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $43,186 | $113,400 | Implemented |
SD0496 # 02 Y:2015 | 02 | 2015 | INSTALL OCCUPANCY SENSORS | $10,851 | $12,449 | Implemented |
SD0496 # 03 Y:2015 | 03 | 2015 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $9,239 | $7,006 | Implemented |
SD0496 # 04 Y:2015 | 04 | 2015 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $5,546 | $18,500 | Not Implemented |
SD0496 # 05 Y:2015 | 05 | 2015 | USE PHOTOCELL CONTROLS | $2,674 | $2,420 | Implemented |
SD0496 # 06 Y:2015 | 06 | 2015 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $869 | $1,356 | Implemented |
SF0461 # 01 Y:2015 | 01 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,239 | $75 | Implemented |
SF0461 # 02 Y:2015 | 02 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,905 | $3,053 | Implemented |
SF0461 # 03 Y:2015 | 03 | 2015 | INSTALL OCCUPANCY SENSORS | $2,517 | $4,371 | Implemented |
SF0461 # 04 Y:2015 | 04 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,570 | $7,605 | Implemented |
SF0461 # 05 Y:2015 | 05 | 2015 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $28,819 | $80,476 | Implemented |
SF0461 # 06 Y:2015 | 06 | 2015 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $231 | $1,000 | Not Implemented |
SF0461 # 07 Y:2015 | 07 | 2015 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $424 | $2,004 | Not Implemented |
SF0461 # 08 Y:2015 | 08 | 2015 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $666 | $50 | Implemented |
SF0459 # 01 Y:2015 | 01 | 2015 | REPAIR OR REPLACE STEAM TRAPS | $29,918 | $5,047 | Implemented |
SF0459 # 02 Y:2015 | 02 | 2015 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $391 | $0 | Implemented |
SF0459 # 03 Y:2015 | 03 | 2015 | MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE | $196,316 | $40,788 | Not Implemented |
SF0459 # 04 Y:2015 | 04 | 2015 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $41,206 | $19,989 | Not Implemented |
SF0459 # 05 Y:2015 | 05 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $23,624 | $15,013 | Not Implemented |
SF0459 # 06 Y:2015 | 06 | 2015 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $23,360 | $14,429 | Implemented |
SF0459 # 07 Y:2015 | 07 | 2015 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $3,292 | $1,945 | Implemented |
SF0459 # 08 Y:2015 | 08 | 2015 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $16,977 | $11,607 | Not Implemented |
SF0459 # 09 Y:2015 | 09 | 2015 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $7,959 | $6,271 | Not Implemented |