Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,777
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
GT0479 # 08 Y:1992 | 08 | 1992 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $88,450 | $133,000 | Not Implemented |
GT0480 # 01 Y:1992 | 01 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $828 | $2,690 | Implemented |
GT0480 # 02 Y:1992 | 02 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $880 | $1,300 | Implemented |
GT0480 # 03 Y:1992 | 03 | 1992 | INSTALL SET-BACK TIMERS | $1,675 | $500 | Implemented |
GT0480 # 04 Y:1992 | 04 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $650 | $2,860 | Implemented |
GT0480 # 05 Y:1992 | 05 | 1992 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $2,900 | $7,000 | Implemented |
GT0481 # 01 Y:1992 | 01 | 1992 | ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO | $2,300 | $900 | Implemented |
GT0481 # 02 Y:1992 | 02 | 1992 | INCREASE AMOUNT OF CONDENSATE RETURNED | $23,265 | $7,500 | Implemented |
GT0481 # 03 Y:1992 | 03 | 1992 | USE COMPUTER PROGRAMS TO OPTIMIZE HVAC PERFORMANCE | $46,920 | $60,000 | Implemented |
GT0481 # 04 Y:1992 | 04 | 1992 | RECOVER AND REUSE COOLING WATER | $5,790 | $800 | Implemented |
GT0481 # 05 Y:1992 | 05 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $498 | $2,540 | Implemented |
GT0481 # 06 Y:1992 | 06 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $545 | $0 | Implemented |
GT0481 # 07 Y:1992 | 07 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,197 | $7,700 | Implemented |
GT0481 # 08 Y:1992 | 08 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $37,700 | $40,240 | Implemented |
GT0481 # 09 Y:1992 | 09 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,814 | $22,050 | Implemented |
GT0481 # 10 Y:1992 | 10 | 1992 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $175,445 | $450,000 | Implemented |
GT0482 # 01 Y:1992 | 01 | 1992 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $8,400 | $190,520 | Implemented |
GT0482 # 02 Y:1992 | 02 | 1992 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $11,250 | $0 | Implemented |
GT0482 # 03 Y:1992 | 03 | 1992 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $815 | $2,520 | Implemented |
GT0482 # 04 Y:1992 | 04 | 1992 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $1,390 | $1,250 | Implemented |
GT0482 # 05 Y:1992 | 05 | 1992 | DISCONNECT BALLASTS | $400 | $0 | Implemented |
GT0482 # 06 Y:1992 | 06 | 1992 | USE FOSSIL FUEL POWERED GENERATOR DURING PEAK DEMAND PERIODS | $141,380 | $750,000 | Implemented |
KU0390 # 04 Y:1992 | 04 | 1992 | BURN A LESS EXPENSIVE GRADE OF FUEL | $4,504 | $0 | Implemented |
KU0390 # 05 Y:1992 | 05 | 1992 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,643 | $3,800 | Implemented |
KU0390 # 06 Y:1992 | 06 | 1992 | USE HOT PROCESS FLUIDS TO PREHEAT INCOMING PROCESS FLUIDS | $3,635 | $5,600 | Not Implemented |