Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,520
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0254 # 08 Y:1999 | 08 | 1999 | INITIATE A TOTAL QUALITY MANAGEMENT PROGRAM | $51,100 | $13,200 | Implemented |
AS0253 # 01 Y:1999 | 01 | 1999 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,900 | $4,824 | Not Implemented |
AS0253 # 02 Y:1999 | 02 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,416 | $160 | Not Implemented |
AS0253 # 03 Y:1999 | 03 | 1999 | REPLACE EXISTING HVAC UNIT WITH HIGH EFFICIENCY MODEL | $1,563 | $1,200 | Not Implemented |
AS0253 # 04 Y:1999 | 04 | 1999 | INSTALL TIMERS AND/OR THERMOSTATS | $428 | $225 | Implemented |
AS0253 # 05 Y:1999 | 05 | 1999 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $468 | $560 | Implemented |
AS0253 # 06 Y:1999 | 06 | 1999 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $1,296 | $60 | Not Implemented |
AS0253 # 07 Y:1999 | 07 | 1999 | USE A LESS EXPENSIVE METHOD OF WASTE REMOVAL | $1,611 | $1,060 | Implemented |
AS0253 # 08 Y:1999 | 08 | 1999 | PAY BILLS ON TIME TO AVOID LATE FEES | $780 | $60 | Implemented |
AS0253 # 09 Y:1999 | 09 | 1999 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $2,737 | $270 | Not Implemented |
SD0226 # 01 Y:1999 | 01 | 1999 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,751 | $4,040 | Implemented |
SD0226 # 02 Y:1999 | 02 | 1999 | INSTALL SPECTRAL REFLECTORS / DELAMP | $1,824 | $2,400 | Not Implemented |
SD0226 # 03 Y:1999 | 03 | 1999 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,129 | $50 | Implemented |
SD0226 # 04 Y:1999 | 04 | 1999 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,584 | $400 | Implemented |
SD0226 # 05 Y:1999 | 05 | 1999 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $488 | $800 | Not Implemented |
SD0226 # 06 Y:1999 | 06 | 1999 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $3,751 | $0 | Implemented |
SD0226 # 07 Y:1999 | 07 | 1999 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $73,351 | $169,125 | Not Implemented |
SD0226 # 08 Y:1999 | 08 | 1999 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $903 | $0 | Implemented |
SD0226 # 09 Y:1999 | 09 | 1999 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $1,618 | $0 | Implemented |
SD0226 # 10 Y:1999 | 10 | 1999 | CONVERT TO AQUEOUS CLEANING | $1,362 | $0 | Not Implemented |
SD0226 # 11 Y:1999 | 11 | 1999 | MAINTAIN MACHINES TO REDUCE LEAKS | $1,103 | $385 | Implemented |
SD0226 # 12 Y:1999 | 12 | 1999 | INSTALL BACK-UP EQUIPMENT | $1,728 | $0 | Not Implemented |
NV0131 # 01 Y:1999 | 01 | 1999 | INSULATE BARE EQUIPMENT | $105 | $200 | Not Implemented |
NV0131 # 02 Y:1999 | 02 | 1999 | OPTIMIZE PLANT POWER FACTOR | $1,146 | $1,933 | Not Implemented |
NV0131 # 03 Y:1999 | 03 | 1999 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,277 | $638 | Implemented |