Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,394
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0284 # 08 Y:2004 | 08 | 2004 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,661 | $1,900 | Not Implemented |
SF0284 # 09 Y:2004 | 09 | 2004 | INSTALL OCCUPANCY SENSORS | $554 | $1,152 | Not Implemented |
SF0284 # 10 Y:2004 | 10 | 2004 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $15,103 | $50,000 | Not Implemented |
SF0284 # 11 Y:2004 | 11 | 2004 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $13,300 | $3,000 | Implemented |
TA0075 # 01 Y:2004 | 01 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $15,473 | $150 | Implemented |
TA0075 # 02 Y:2004 | 02 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $12,900 | $771 | Implemented |
TA0075 # 03 Y:2004 | 03 | 2004 | TURN OFF EQUIPMENT WHEN NOT IN USE | $9,615 | $150 | Implemented |
TA0075 # 04 Y:2004 | 04 | 2004 | INSULATE BARE EQUIPMENT | $6,086 | $2,690 | Not Implemented |
TA0075 # 05 Y:2004 | 05 | 2004 | INSTALL SET-BACK TIMERS | $2,163 | $2,350 | Implemented |
TA0075 # 06 Y:2004 | 06 | 2004 | CONTRACT A WOOD PALLET RECYCLING COMPANY | $1,300 | $50 | Implemented |
TA0075 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,288 | $0 | Implemented |
TA0075 # 08 Y:2004 | 08 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,194 | $1,939 | Implemented |
LM0076 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN WATER LINES AND VALVES | $528 | $25 | Implemented |
LM0076 # 02 Y:2004 | 02 | 2004 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $2,952 | $1,300 | Implemented |
LM0076 # 03 Y:2004 | 03 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $255 | $281 | Implemented |
LM0076 # 04 Y:2004 | 04 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $4,953 | $3,825 | Not Implemented |
LM0076 # 05 Y:2004 | 05 | 2004 | REPAIR FAULTY INSULATION IN FURNACES, BOILERS, ETC | $6,736 | $2,500 | Implemented |
LM0076 # 06 Y:2004 | 06 | 2004 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $1,766 | $1,500 | Not Implemented |
LM0076 # 07 Y:2004 | 07 | 2004 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,513 | $880 | Implemented |
MI0079 # 01 Y:2004 | 01 | 2004 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $21,521 | $600 | Not Implemented |
MI0079 # 02 Y:2004 | 02 | 2004 | INSTALL / REPAIR INSULATION ON STEAM LINES | $7,957 | $1,649 | Not Implemented |
MI0079 # 03 Y:2004 | 03 | 2004 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $108,501 | $33,050 | Not Implemented |
MI0079 # 04 Y:2004 | 04 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,693 | $250 | Not Implemented |
MI0079 # 05 Y:2004 | 05 | 2004 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $138,625 | $68,380 | Implemented |
MI0079 # 06 Y:2004 | 06 | 2004 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $19,937 | $61,795 | Not Implemented |