IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

5,333

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
CO0476 # 05 Y:2000 05 2000 DISTILL CONTAMINATED SOLVENTS FOR REUSE $16,290 $13,500 Not Implemented
CO0476 # 06 Y:2000 06 2000 USE FILTER AND DRYING OVEN TO REDUCE SLUDGE VOLUME $6,490 $41,000 Not Implemented
OR0382 # 01 Y:2000 01 2000 ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS $26,817 $900 Implemented
OR0382 # 02 Y:2000 02 2000 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $15,208 $26,491 Implemented
OR0382 # 03 Y:2000 03 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $4,194 $2,979 Not Implemented
OR0382 # 04 Y:2000 04 2000 MODIFY REFRIGERATION SYSTEM TO OPERATE AT A LOWER PRESSURE $2,050 $4,653 Not Implemented
OR0382 # 05 Y:2000 05 2000 OPTIMIZE PLANT POWER FACTOR $2,241 $6,400 Not Implemented
OR0382 # 06 Y:2000 06 2000 ELIMINATE A BY-PRODUCT $68,235 $2,000 Implemented
BD0175 # 01 Y:2000 01 2000 INSTALL OCCUPANCY SENSORS $4,078 $2,850 Implemented
BD0175 # 02 Y:2000 02 2000 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,783 $0 Not Implemented
BD0175 # 03 Y:2000 03 2000 RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS $1,116 $0 Not Implemented
BD0175 # 04 Y:2000 04 2000 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $599 $1,000 Implemented
BD0175 # 05 Y:2000 05 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $361 $338 Implemented
BD0175 # 06 Y:2000 06 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $92,187 $250,000 Not Implemented
BD0175 # 07 Y:2000 07 2000 INCREASE USE OF AUTOMATION $226,800 $45,735 Not Implemented
BD0175 # 08 Y:2000 08 2000 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER $8,400 $10,000 Not Implemented
BD0174 # 01 Y:2000 01 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $3,817 $2,695 Implemented
BD0174 # 02 Y:2000 02 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $2,542 $2,000 Implemented
BD0174 # 03 Y:2000 03 2000 INSTALL OCCUPANCY SENSORS $2,138 $1,800 Implemented
BD0174 # 04 Y:2000 04 2000 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $487 $385 Implemented
BD0174 # 05 Y:2000 05 2000 LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER $1,090 $400 Implemented
BD0174 # 06 Y:2000 06 2000 REUSE / RECYCLE/ SELL PAPER PRODUCTS $854 $250 Implemented
BD0174 # 07 Y:2000 07 2000 INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE $526 $500 Implemented
BD0174 # 08 Y:2000 08 2000 ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK $218,400 $61,810 Implemented
BD0174 # 09 Y:2000 09 2000 CLEAR AND RENT EXISTING SPACE $45,120 $20,000 Not Implemented