Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,640
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OK0612 # 05 Y:2001 | 05 | 2001 | REPAIR AND ELIMINATE STEAM LEAKS | $1,650 | $720 | Implemented |
OK0612 # 06 Y:2001 | 06 | 2001 | OPTIMIZE PLANT POWER FACTOR | $14,115 | $5,150 | Not Implemented |
WI0395 # 01 Y:2001 | 01 | 2001 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $11,007 | $0 | Not Implemented |
WI0395 # 02 Y:2001 | 02 | 2001 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,031 | $17,436 | n/a |
WI0395 # 03 Y:2001 | 03 | 2001 | INSTALL OCCUPANCY SENSORS | $1,563 | $1,800 | Implemented |
WI0395 # 04 Y:2001 | 04 | 2001 | INSTALL OCCUPANCY SENSORS | $320 | $350 | Implemented |
WI0395 # 05 Y:2001 | 05 | 2001 | USE WASTE HEAT FROM FLUE GASES TO HEAT SPACE CONDITIONING AIR | $2,257 | $6,000 | Implemented |
WI0395 # 06 Y:2001 | 06 | 2001 | RECOVER WASTE HEAT FROM EQUIPMENT | $1,627 | $500 | Not Implemented |
WI0395 # 07 Y:2001 | 07 | 2001 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $935 | $640 | Not Implemented |
WI0395 # 08 Y:2001 | 08 | 2001 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $163 | $60 | Not Implemented |
TA0005 # 01 Y:2001 | 01 | 2001 | ELIMINATE/REDUCE AN OPERATION | $69,313 | $0 | Implemented |
TA0005 # 02 Y:2001 | 02 | 2001 | INCREASE AMOUNT OF CONDENSATE RETURNED | $55,066 | $8,241 | n/a |
TA0005 # 03 Y:2001 | 03 | 2001 | REDUCE EXCESS STEAM BLEEDING | $32,800 | $156 | Not Implemented |
TA0005 # 04 Y:2001 | 04 | 2001 | REPAIR AND ELIMINATE STEAM LEAKS | $31,880 | $1,080 | Implemented |
TA0005 # 05 Y:2001 | 05 | 2001 | $17,010 | $0 | Implemented | |
TA0005 # 06 Y:2001 | 06 | 2001 | REDUCE EXCESS STEAM BLEEDING | $14,571 | $155 | Implemented |
TA0005 # 07 Y:2001 | 07 | 2001 | INSULATE BARE EQUIPMENT | $14,688 | $20,194 | Implemented |
TA0005 # 08 Y:2001 | 08 | 2001 | SUBSTITUTE HOT PROCESS FLUIDS FOR STEAM | $6,882 | $820 | Implemented |
TA0005 # 09 Y:2001 | 09 | 2001 | USE SYNTHETIC LUBRICANT | $3,975 | $0 | Not Implemented |
TA0005 # 10 Y:2001 | 10 | 2001 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $3,293 | $35 | Implemented |
TA0005 # 11 Y:2001 | 11 | 2001 | $1,998 | $0 | Implemented | |
TA0005 # 12 Y:2001 | 12 | 2001 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,855 | $277 | Implemented |
TA0005 # 13 Y:2001 | 13 | 2001 | INSTALL / REPAIR INSULATION ON STEAM LINES | $1,580 | $826 | Implemented |
TA0005 # 14 Y:2001 | 14 | 2001 | INSULATE BARE EQUIPMENT | $258 | $249 | Not Implemented |
BD0187 # 01 Y:2001 | 01 | 2001 | USE RADIANT HEATER FOR SPOT HEATING | $15,187 | $19,000 | Not Implemented |