Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
94,135
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0480 # 02 Y:2005 | 02 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,175 | $3,200 | Implemented |
OR0480 # 03 Y:2005 | 03 | 2005 | ESTABLISH BURNER MAINTENANCE SCHEDULE FOR BOILERS | $493 | $0 | Implemented |
OR0480 # 04 Y:2005 | 04 | 2005 | OPTIMIZE PLANT POWER FACTOR | $1,910 | $2,000 | Not Implemented |
AS0397 # 01 Y:2005 | 01 | 2005 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $19,864 | $15,000 | Not Implemented |
AS0397 # 02 Y:2005 | 02 | 2005 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $7,302 | $1,000 | Not Implemented |
AS0397 # 03 Y:2005 | 03 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,147 | $6,757 | Not Implemented |
AS0397 # 04 Y:2005 | 04 | 2005 | REDUCE SCRAP PRODUCTION | $474 | $150 | Not Implemented |
AS0397 # 05 Y:2005 | 05 | 2005 | INSULATE BARE EQUIPMENT | $520 | $250 | Not Implemented |
SD0358 # 01 Y:2005 | 01 | 2005 | REPLACE OBSOLETE BURNERS WITH MORE EFFICIENT ONES | $10,212 | $3,850 | Not Implemented |
SD0358 # 02 Y:2005 | 02 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $5,194 | $360 | Implemented |
SD0358 # 03 Y:2005 | 03 | 2005 | TURN OFF EQUIPMENT WHEN NOT IN USE | $980 | $76 | Not Implemented |
SD0358 # 04 Y:2005 | 04 | 2005 | LOWER OPERATING PRESSURE OF CONDENSER (STEAM) | $593 | $0 | Not Implemented |
SD0358 # 05 Y:2005 | 05 | 2005 | REPAIR AND ELIMINATE STEAM LEAKS | $550 | $1,050 | Implemented |
SD0358 # 06 Y:2005 | 06 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,023 | $37,287 | Implemented |
SD0358 # 07 Y:2005 | 07 | 2005 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $13,768 | $18,500 | Not Implemented |
SD0358 # 08 Y:2005 | 08 | 2005 | CONSIDER USE / PURCHASE OF BULK MATERIALS WHERE POSSIBLE | $37,125 | $52,500 | Implemented |
LM0094 # 01 Y:2005 | 01 | 2005 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,130 | $500 | Implemented |
LM0094 # 02 Y:2005 | 02 | 2005 | INSTALL / REPAIR INSULATION ON STEAM LINES | $2,502 | $983 | Implemented |
LM0094 # 03 Y:2005 | 03 | 2005 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $57,780 | $50,000 | Implemented |
LM0094 # 04 Y:2005 | 04 | 2005 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,187 | $34,080 | Not Implemented |
LM0094 # 05 Y:2005 | 05 | 2005 | UTILIZE DAYLIGHT WHENEVER POSSIBLE IN LIEU OF ARTIFICIAL LIGHT | $2,628 | $0 | Not Implemented |
CO0559 # 01 Y:2004 | 01 | 2004 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,070 | $440 | Implemented |
CO0559 # 02 Y:2004 | 02 | 2004 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $355 | $416 | Implemented |
CO0559 # 03 Y:2004 | 03 | 2004 | USE DEMAND CONTROLLER OR LOAD SHEDDER | $1,190 | $740 | Implemented |
CO0559 # 04 Y:2004 | 04 | 2004 | UTILIZE OUTSIDE AIR INSTEAD OF CONDITIONED AIR FOR DRYING | $1,180 | $810 | Implemented |