Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,708
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0248 # 02 Y:2002 | 02 | 2002 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $9,169 | $1,436 | Not Implemented |
SF0248 # 03 Y:2002 | 03 | 2002 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $1,713 | $1,685 | Implemented |
SF0248 # 04 Y:2002 | 04 | 2002 | USE PHOTOCELL CONTROLS | $5,341 | $6,000 | Implemented |
SF0248 # 05 Y:2002 | 05 | 2002 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $513 | $700 | Not Implemented |
SF0248 # 06 Y:2002 | 06 | 2002 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $2,409 | $13,000 | Implemented |
SF0248 # 07 Y:2002 | 07 | 2002 | REDUCE / ELIMINATE USE OF DISPOSABLE PRODUCT | $840 | $0 | Not Implemented |
IC0046 # 01 Y:2002 | 01 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $720 | $1,900 | Implemented |
IC0046 # 02 Y:2002 | 02 | 2002 | RECOVER WASTE HEAT FROM EQUIPMENT | $3,889 | $0 | Not Implemented |
IC0046 # 03 Y:2002 | 03 | 2002 | INSULATE BARE EQUIPMENT | $30,483 | $53,653 | Not Implemented |
IC0046 # 04 Y:2002 | 04 | 2002 | INSULATE BARE EQUIPMENT | $6,403 | $11,922 | Not Implemented |
IC0046 # 05 Y:2002 | 05 | 2002 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $1,140 | $0 | Implemented |
IC0046 # 06 Y:2002 | 06 | 2002 | REDUCE OR ELIMINATE WASTE | $36,204 | $27,704 | Implemented |
IC0046 # 07 Y:2002 | 07 | 2002 | AUTOMATE PAYROLL SYSTEM | $58,887 | $6,196 | Implemented |
IC0046 # 08 Y:2002 | 08 | 2002 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $2,460 | $1,600 | Implemented |
IC0045 # 01 Y:2002 | 01 | 2002 | MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED | $7,422 | $1,320 | n/a |
IC0045 # 02 Y:2002 | 02 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,857 | $7,199 | n/a |
IC0045 # 03 Y:2002 | 03 | 2002 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $13,831 | $62,835 | n/a |
IC0045 # 04 Y:2002 | 04 | 2002 | INSTALL OCCUPANCY SENSORS | $4,970 | $12,088 | n/a |
IC0045 # 05 Y:2002 | 05 | 2002 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $251 | $223 | n/a |
IC0045 # 06 Y:2002 | 06 | 2002 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $166 | $635 | n/a |
IC0045 # 07 Y:2002 | 07 | 2002 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $910 | $625 | n/a |
IC0045 # 08 Y:2002 | 08 | 2002 | RECOVER WASTE HEAT FROM EQUIPMENT | $990 | $734 | n/a |
IC0045 # 09 Y:2002 | 09 | 2002 | CHANGE RATE SCHEDULES OR OTHER CHANGES IN UTILITY SERVICE | $36,638 | $0 | n/a |
SU0146 # 01 Y:2002 | 01 | 2002 | DEMOLISH OLD BUILDING TO REDUCE TAX AND INSURANCE BILLS | $18,266 | $35,000 | Not Implemented |
SU0146 # 02 Y:2002 | 02 | 2002 | REUSE / RECYCLE/ SELL PAPER PRODUCTS | $16,051 | $38,750 | Not Implemented |