Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,105
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
UD0664 # 10 Y:2003 | 10 | 2003 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $3,280 | $378 | Not Implemented |
UD0664 # 11 Y:2003 | 11 | 2003 | DISCONNECT BALLASTS | $2,820 | $250 | Implemented |
UD0664 # 12 Y:2003 | 12 | 2003 | INSULATE BARE EQUIPMENT | $1,414 | $1,800 | Not Implemented |
UD0664 # 13 Y:2003 | 13 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,219 | $0 | Not Implemented |
UD0664 # 14 Y:2003 | 14 | 2003 | IMPROVE COMBUSTION CONTROL CAPABILITY | $247 | $25 | Not Implemented |
UD0664 # 15 Y:2003 | 15 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $178 | $0 | Implemented |
UD0664 # 16 Y:2003 | 16 | 2003 | MINIMIZE NON-ESSENTIAL MATERIAL IN HEAT TREATMENT PROCESS | $112 | $0 | Not Implemented |
MI0053 # 01 Y:2003 | 01 | 2003 | METER WASTE WATER | $1,881 | $1,454 | Not Implemented |
MI0053 # 02 Y:2003 | 02 | 2003 | BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE | $35,000 | $7,660 | Implemented |
MI0053 # 03 Y:2003 | 03 | 2003 | RE-USE OR RECYCLE HOT OR COLD PROCESS EXHAUST AIR | $4,563 | $654 | Not Implemented |
MI0053 # 04 Y:2003 | 04 | 2003 | INSTALL OCCUPANCY SENSORS | $7,089 | $885 | Not Implemented |
MI0053 # 05 Y:2003 | 05 | 2003 | TURN OFF EQUIPMENT WHEN NOT IN USE | $1,991 | $169 | Implemented |
MI0053 # 06 Y:2003 | 06 | 2003 | PAY BILLS ON TIME TO AVOID LATE FEES | $4,115 | $0 | Implemented |
SF0255 # 01 Y:2003 | 01 | 2003 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,228 | $140 | Implemented |
SF0255 # 02 Y:2003 | 02 | 2003 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $9,649 | $3,715 | Not Implemented |
SF0255 # 03 Y:2003 | 03 | 2003 | USE COOLING TOWER WATER INSTEAD OF REFRIGERATION | $7,212 | $5,250 | Not Implemented |
SF0255 # 04 Y:2003 | 04 | 2003 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $2,226 | $3,400 | Implemented |
SF0255 # 05 Y:2003 | 05 | 2003 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $6,416 | $13,464 | Not Implemented |
SF0255 # 06 Y:2003 | 06 | 2003 | INSTALL OCCUPANCY SENSORS | $3,302 | $7,220 | Not Implemented |
SF0255 # 07 Y:2003 | 07 | 2003 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $353 | $796 | Implemented |
SF0255 # 08 Y:2003 | 08 | 2003 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $12,337 | $587 | Not Implemented |
SF0255 # 09 Y:2003 | 09 | 2003 | OPTIMIZE PLANT POWER FACTOR | $678 | $1,749 | Not Implemented |
OK0657 # 01 Y:2003 | 01 | 2003 | INSTALL OCCUPANCY SENSORS | $1,116 | $722 | Not Implemented |
OK0657 # 02 Y:2003 | 02 | 2003 | RESCHEDULE PLANT OPERATIONS OR REDUCE LOAD TO AVOID PEAKS | $2,220 | $25 | Implemented |
OK0657 # 03 Y:2003 | 03 | 2003 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $10,257 | $320 | Implemented |