Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,996
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MS0083 # 04 Y:1997 | 04 | 1997 | BURN WASTE OIL FOR HEAT | $1,022 | $1,995 | Not Implemented |
MS0083 # 05 Y:1997 | 05 | 1997 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $480,511 | $9,400 | Not Implemented |
KG0087 # 01 Y:1997 | 01 | 1997 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,696 | $75 | n/a |
KG0087 # 02 Y:1997 | 02 | 1997 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $2,241 | $290 | n/a |
KG0087 # 03 Y:1997 | 03 | 1997 | INSTALL TIMERS AND/OR THERMOSTATS | $1,809 | $1,200 | n/a |
KG0087 # 04 Y:1997 | 04 | 1997 | INSTALL TIMERS AND/OR THERMOSTATS | $1,689 | $1,050 | n/a |
KG0087 # 05 Y:1997 | 05 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $771 | $341 | n/a |
KG0087 # 06 Y:1997 | 06 | 1997 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $33,414 | $0 | n/a |
KG0087 # 07 Y:1997 | 07 | 1997 | INCREASE AMOUNT OF WASTE RECOVERED FOR RESALE | $11,385 | $360 | n/a |
KG0087 # 08 Y:1997 | 08 | 1997 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $2,822,400 | $686,200 | n/a |
KG0087 # 09 Y:1997 | 09 | 1997 | REPLACE OLD MACHINE WITH NEW AUTOMATIC MULTI-STATION TOOL | $646,464 | $0 | n/a |
HO0154 # 01 Y:1997 | 01 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $5,944 | $21,668 | Implemented |
HO0154 # 02 Y:1997 | 02 | 1997 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $178 | $575 | Not Implemented |
HO0154 # 03 Y:1997 | 03 | 1997 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $6,425 | $3,182 | Not Implemented |
HO0154 # 04 Y:1997 | 04 | 1997 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE LABOR COSTS | $15,600 | $10,800 | Not Implemented |
HO0154 # 05 Y:1997 | 05 | 1997 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $117,000 | $525,000 | Not Implemented |
HO0154 # 06 Y:1997 | 06 | 1997 | USE EVAPORATION TO CONCENTRATE MATERIAL | $2,563 | $10,000 | Implemented |
IA0164 # 01 Y:1997 | 01 | 1997 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $32,289 | $800 | Implemented |
IA0164 # 02 Y:1997 | 02 | 1997 | INSTALL FOSSIL FUEL MAKE-UP AIR UNIT | $17,815 | $19,000 | Not Implemented |
IA0164 # 03 Y:1997 | 03 | 1997 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $944 | $898 | Implemented |
IA0164 # 04 Y:1997 | 04 | 1997 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,481 | $268 | Implemented |
IA0164 # 05 Y:1997 | 05 | 1997 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,647 | $20 | Implemented |
IA0164 # 06 Y:1997 | 06 | 1997 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $5,860 | $1,788 | Implemented |
IA0164 # 07 Y:1997 | 07 | 1997 | CONVERT TO ELECTROSTATIC POWDER COATING | $4,848 | $8,000 | Implemented |
IA0164 # 08 Y:1997 | 08 | 1997 | USE FIXTURES TO REDUCE MACHINE CHANGEOUT TIMES | $5,894 | $100 | Implemented |