Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,568
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
OR0628 # 04 Y:2014 | 04 | 2014 | REPLACE EXISTING EQUIPMENT WITH MORE SUITABLE SUBSTITUTES | $25,006 | $4,810 | Not Implemented |
OR0628 # 05 Y:2014 | 05 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,875 | $1,293 | Not Implemented |
OR0628 # 06 Y:2014 | 06 | 2014 | UPGRADE CONVEYORS | $20,000 | $11,206 | Not Implemented |
OR0628 # 07 Y:2014 | 07 | 2014 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $9,718 | $2,460 | Implemented |
OR0628 # 08 Y:2014 | 08 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $877 | $500 | Not Implemented |
OR0628 # 09 Y:2014 | 09 | 2014 | REPLACE HYDRAULIC / PNEUMATIC EQUIPMENT WITH ELECTRIC EQUIPMENT | $948 | $676 | Not Implemented |
OR0626 # 01 Y:2014 | 01 | 2014 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $18,202 | $6,792 | Not Implemented |
OR0626 # 02 Y:2014 | 02 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,945 | $1,000 | Not Implemented |
OR0626 # 03 Y:2014 | 03 | 2014 | IMPROVE COMBUSTION CONTROL CAPABILITY | $11,422 | $7,219 | Not Implemented |
OR0626 # 04 Y:2014 | 04 | 2014 | UPGRADE CONTROLS ON COMPRESSORS | $7,138 | $5,500 | Not Implemented |
OR0626 # 05 Y:2014 | 05 | 2014 | RECOVER HEAT FROM EXHAUSTED STEAM, HOT AIR OR HOT WATER | $5,445 | $6,461 | Not Implemented |
OR0626 # 06 Y:2014 | 06 | 2014 | INSULATE BARE EQUIPMENT | $3,138 | $5,659 | Not Implemented |
OR0626 # 07 Y:2014 | 07 | 2014 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,463 | $3,437 | Not Implemented |
OR0625 # 01 Y:2014 | 01 | 2014 | TURN OFF EQUIPMENT WHEN NOT IN USE | $11,654 | $1,000 | Not Implemented |
OR0625 # 02 Y:2014 | 02 | 2014 | UTILIZE A LESS EXPENSIVE COOLING METHOD | $5,751 | $5,908 | Not Implemented |
OR0625 # 03 Y:2014 | 03 | 2014 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,834 | $800 | Not Implemented |
OR0625 # 04 Y:2014 | 04 | 2014 | USE SOLAR HEAT TO MAKE ELECTRICTY | $5,889 | $72,131 | Not Implemented |
OR0625 # 05 Y:2014 | 05 | 2014 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $5,528 | $0 | Not Implemented |
OR0625 # 06 Y:2014 | 06 | 2014 | REDUCE FLUID FLOW RATES | $2,097 | $5,600 | Not Implemented |
OR0622 # 01 Y:2013 | 01 | 2013 | IMPROVE COMBUSTION CONTROL CAPABILITY | $9,626 | $1,814 | Not Implemented |
OR0622 # 02 Y:2013 | 02 | 2013 | UPGRADE CONTROLS ON COMPRESSORS | $10,631 | $10,763 | Not Implemented |
OR0622 # 03 Y:2013 | 03 | 2013 | USE HEAT FROM BOILER BLOWDOWN TO PREHEAT BOILER FEED WATER | $8,423 | $20,917 | Not Implemented |
OR0622 # 04 Y:2013 | 04 | 2013 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $7,279 | $15,410 | Not Implemented |
OR0618 # 01 Y:2013 | 01 | 2013 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $2,881 | $3,300 | Not Implemented |
OR0618 # 02 Y:2013 | 02 | 2013 | MODIFY STARTUP/SHUTDOWN TIMES | $10,380 | $800 | Not Implemented |