Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
4,204
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TA0131 # 02 Y:2006 | 02 | 2006 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $9,225 | $60 | Not Implemented |
TA0131 # 03 Y:2006 | 03 | 2006 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $4,180 | $630 | Not Implemented |
TA0131 # 04 Y:2006 | 04 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $2,450 | $120 | Implemented |
TA0131 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $15,400 | $0 | Implemented |
TA0130 # 01 Y:2006 | 01 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $17,192 | $0 | Implemented |
TA0130 # 02 Y:2006 | 02 | 2006 | INSTALL / REPAIR INSULATION ON STEAM LINES | $81 | $252 | Implemented |
TA0130 # 03 Y:2006 | 03 | 2006 | OPTIMIZE PLANT POWER FACTOR | $10,795 | $22,000 | Implemented |
OR0511 # 09 Y:2006 | 09 | 2006 | SIZE ELECTRIC MOTORS FOR PEAK OPERATING EFFICIENCY | $2,400 | $2,600 | Not Implemented |
OR0511 # 08 Y:2006 | 08 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $3,600 | $5,000 | Implemented |
OR0511 # 07 Y:2006 | 07 | 2006 | REPLACE EXISTING CHILLER WITH HIGH EFFICIENCY MODEL | $3,800 | $4,500 | Not Implemented |
OR0511 # 06 Y:2006 | 06 | 2006 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $6,300 | $6,300 | Implemented |
OR0511 # 05 Y:2006 | 05 | 2006 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $10,800 | $0 | Implemented |
OR0511 # 04 Y:2006 | 04 | 2006 | INSTALL DIRECT ACTING UNITS IN PLACE OF COMPRESSED AIR PRESSURE SYSTEM IN SAFETY SYSTEM | $14,400 | $13,700 | Implemented |
OR0511 # 03 Y:2006 | 03 | 2006 | RECOVER WASTE HEAT FROM EQUIPMENT | $10,500 | $7,340 | Not Implemented |
OR0511 # 02 Y:2006 | 02 | 2006 | REDUCE COMBUSTION AIR FLOW TO OPTIMUM | $35,500 | $8,000 | Implemented |
OR0511 # 01 Y:2006 | 01 | 2006 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $1,200,000 | $400,000 | Implemented |
UF0393 # 09 Y:2006 | 09 | 2006 | TURN OFF EQUIPMENT WHEN NOT IN USE | $643 | $0 | Implemented |
UF0393 # 08 Y:2006 | 08 | 2006 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $8,457 | $0 | Not Implemented |
UF0393 # 07 Y:2006 | 07 | 2006 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $19,036 | $27,664 | Not Implemented |
UF0393 # 06 Y:2006 | 06 | 2006 | INSTALL OCCUPANCY SENSORS | $1,990 | $227 | Implemented |
UF0393 # 05 Y:2006 | 05 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $14,705 | $62,192 | Not Implemented |
UF0393 # 04 Y:2006 | 04 | 2006 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $6,417 | $10,049 | Not Implemented |
UF0393 # 03 Y:2006 | 03 | 2006 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $3,158 | $1,938 | Not Implemented |
UF0393 # 02 Y:2006 | 02 | 2006 | OPTIMIZE PLANT POWER FACTOR | $24,700 | $17,000 | Not Implemented |
UF0393 # 01 Y:2006 | 01 | 2006 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $37,010 | $71,812 | Not Implemented |