Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
2,969
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
MA0673 # 02 Y:2011 | 02 | 2011 | USE MINIMUM SAFE OVEN VENTILATION | $3,752 | $490 | Not Implemented |
MA0673 # 03 Y:2011 | 03 | 2011 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $3,772 | $540 | Implemented |
MA0673 # 04 Y:2011 | 04 | 2011 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $3,179 | $8,435 | Not Implemented |
MA0673 # 05 Y:2011 | 05 | 2011 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $1,432 | $6,475 | Not Implemented |
MA0673 # 06 Y:2011 | 06 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,078 | $200 | Implemented |
MA0673 # 07 Y:2011 | 07 | 2011 | INSTALL OCCUPANCY SENSORS | $743 | $1,800 | Not Implemented |
MA0673 # 08 Y:2011 | 08 | 2011 | INSULATE BARE EQUIPMENT | $386 | $450 | Not Implemented |
MA0671 # 01 Y:2011 | 01 | 2011 | USE A FOSSIL FUEL ENGINE TO COGENERATE ELECTRICITY OR MOTIVE POWER; AND UTILIZE HEAT | $36,635 | $200,000 | Not Implemented |
MA0671 # 02 Y:2011 | 02 | 2011 | INSTALL / REPAIR INSULATION ON STEAM LINES | $4,780 | $3,550 | Implemented |
MA0671 # 03 Y:2011 | 03 | 2011 | SHUT OFF COOLING IF COLD OUTSIDE AIR WILL COOL PROCESS | $1,556 | $15,000 | Not Implemented |
MA0671 # 04 Y:2011 | 04 | 2011 | INSTALL OCCUPANCY SENSORS | $1,328 | $2,220 | Not Implemented |
MA0671 # 05 Y:2011 | 05 | 2011 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $740 | $200 | Implemented |
MA0669 # 01 Y:2011 | 01 | 2011 | REPLACE BOILER | $28,774 | $63,300 | Implemented |
MA0669 # 02 Y:2011 | 02 | 2011 | INSULATE BARE EQUIPMENT | $12,439 | $25,000 | Not Implemented |
MA0669 # 03 Y:2011 | 03 | 2011 | OPTIMIZE PLANT POWER FACTOR | $10,179 | $11,190 | Implemented |
MA0669 # 04 Y:2011 | 04 | 2011 | TURN OFF EQUIPMENT WHEN NOT IN USE | $7,848 | $1,500 | Implemented |
MA0669 # 05 Y:2011 | 05 | 2011 | USE / PURCHASE OPTIMUM SIZED COMPRESSOR | $3,576 | $25,250 | Not Implemented |
MA0669 # 06 Y:2011 | 06 | 2011 | INSULATE BARE EQUIPMENT | $736 | $349 | Not Implemented |
MA0669 # 07 Y:2011 | 07 | 2011 | INSULATE BARE EQUIPMENT | $410 | $550 | Implemented |
MA0667 # 09 Y:2011 | 09 | 2011 | USE OPTIMUM SIZE AND CAPACITY EQUIPMENT | $1,515 | $4,000 | Not Implemented |
MA0667 # 10 Y:2011 | 10 | 2011 | INSTALL AUTOMATIC STACK DAMPER | $729 | $180 | Implemented |
MA0667 # 11 Y:2011 | 11 | 2011 | INSULATE BARE EQUIPMENT | $525 | $550 | Not Implemented |
MA0667 # 12 Y:2011 | 12 | 2011 | INSULATE BARE EQUIPMENT | $98 | $201 | Not Implemented |
MA0667 # 01 Y:2011 | 01 | 2011 | REDUCE VENTILATION AIR | $45,912 | $17,705 | Not Implemented |
MA0667 # 02 Y:2011 | 02 | 2011 | IMPROVE COMBUSTION CONTROL CAPABILITY | $31,118 | $100,000 | Not Implemented |