IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

906

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
OR0419 # 03 Y:2002 03 2002 USE / PURCHASE OPTIMUM SIZED COMPRESSOR $6,988 $3,240 Implemented
OR0419 # 04 Y:2002 04 2002 INSULATE BARE EQUIPMENT $1,581 $1,500 Not Implemented
OR0419 # 05 Y:2002 05 2002 MAKE A PRACTICE OF TURNING OFF LIGHTS WHEN NOT NEEDED $1,587 $0 Implemented
OR0401 # 01 Y:2001 01 2001 OPTIMIZE PLANT POWER FACTOR $76,739 $50,000 Implemented
OR0401 # 02 Y:2001 02 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $6,160 $6,000 Implemented
OR0401 # 03 Y:2001 03 2001 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $56,333 $68,000 Implemented
OR0401 # 04 Y:2001 04 2001 RECOVER WASTE HEAT FROM EQUIPMENT $560,470 $690,000 Not Implemented
OR0401 # 05 Y:2001 05 2001 INSTALL SENSORS TO DETECT DEFECTS $524,500 $2,000,000 Not Implemented
OR0401 # 06 Y:2001 06 2001 DEVELOP STANDARD PROCEDURES TO IMPROVE INTERNAL YIELDS $473,166 $120,000 Not Implemented
OR0401 # 07 Y:2001 07 2001 ELIMINATE OLD STOCK AND MODIFY INVENTORY CONTROL $270,000 $50,000 Not Implemented
OR0400 # 01 Y:2001 01 2001 PURCHASE NEW EQUIPMENT TO REDUCE MATERIAL USE / COST $210,300 $750,000 Not Implemented
OR0400 # 02 Y:2001 02 2001 USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS $7,142 $20,166 Implemented
OR0400 # 03 Y:2001 03 2001 OPTIMIZE PLANT POWER FACTOR $5,776 $5,800 Implemented
OR0400 # 04 Y:2001 04 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,210 $3,200 Implemented
OR0400 # 05 Y:2001 05 2001 UPGRADE CONTROLS ON COMPRESSORS $7,043 $20,800 Not Implemented
OR0399 # 01 Y:2001 01 2001 OPTIMIZE PLANT POWER FACTOR $11,030 $9,500 Not Implemented
OR0399 # 02 Y:2001 02 2001 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $22,410 $98,120 Implemented
OR0399 # 03 Y:2001 03 2001 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $3,926 $4,000 Not Implemented
OR0399 # 04 Y:2001 04 2001 USE OPTIMUM SIZE AND CAPACITY EQUIPMENT $4,029 $18,400 Not Implemented
OR0399 # 05 Y:2001 05 2001 USE OR REPLACE WITH ENERGY EFFICIENT SUBSTITUTES $1,390 $6,063 Not Implemented
OR0376 # 01 Y:2000 01 2000 OPTIMIZE PLANT POWER FACTOR $17,792 $24,000 n/a
OR0376 # 02 Y:2000 02 2000 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $6,330 $44,000 n/a
OR0376 # 03 Y:2000 03 2000 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $4,246 $6,825 n/a
OR0376 # 04 Y:2000 04 2000 USE PHOTOCELL CONTROLS $986 $700 n/a
OR0374 # 01 Y:2000 01 2000 CHANGE PRODUCT DESIGN TO REDUCE ENERGY REQUIREMENTS $152,880 $600,000 Not Implemented