Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
3,718
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
SF0591 # 09 Y:2022 | 09 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $5,521 | $18,051 | Implemented |
SF0591 # 10 Y:2022 | 10 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $47,418 | $177,700 | Not Implemented |
SF0591 # 11 Y:2022 | 11 | 2022 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $35,700 | $132,000 | Not Implemented |
OR0761 # 01 Y:2022 | 01 | 2022 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,913 | $1,078 | Implemented |
OR0761 # 02 Y:2022 | 02 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $9,934 | $9,934 | Implemented |
OR0761 # 03 Y:2022 | 03 | 2022 | OPTIMIZE PLANT POWER FACTOR | $6,236 | $26,406 | Not Implemented |
OR0761 # 04 Y:2022 | 04 | 2022 | MODIFY FACILITY TO AVOID EXCESS MAINTENANCE COSTS | $31,013 | $150,000 | Not Implemented |
CI0002 # 01 Y:2022 | 01 | 2022 | ADJUST / MAINTAIN FORK LIFT TRUCKS FOR MOST EFFICIENT OPERATION | $33,479 | $80,000 | n/a |
CI0002 # 02 Y:2022 | 02 | 2022 | INSULATE GLAZING, WALLS, CEILINGS, AND ROOFS | $27,300 | $24,600 | n/a |
CI0002 # 03 Y:2022 | 03 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $18,201 | $1,800 | n/a |
CI0002 # 04 Y:2022 | 04 | 2022 | ELIMINATE OR REDUCE COMPRESSED AIR USAGE | $12,649 | $30,000 | n/a |
CI0002 # 05 Y:2022 | 05 | 2022 | UPGRADE CONVEYORS | $3,825 | $8,040 | n/a |
CI0002 # 06 Y:2022 | 06 | 2022 | TURN OFF EQUIPMENT WHEN NOT IN USE | $3,680 | $0 | n/a |
CI0002 # 07 Y:2022 | 07 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,733 | $2,167 | n/a |
CI0002 # 08 Y:2022 | 08 | 2022 | INSTALL OCCUPANCY SENSORS | $1,717 | $2,625 | n/a |
CI0002 # 09 Y:2022 | 09 | 2022 | USE PHOTOCELL CONTROLS | $1,322 | $1,350 | n/a |
UL2212 # 01 Y:2022 | 01 | 2022 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $12,840 | $16,294 | Not Implemented |
UL2212 # 02 Y:2022 | 02 | 2022 | INSTALL OCCUPANCY SENSORS | $1,208 | $2,171 | Not Implemented |
UL2212 # 03 Y:2022 | 03 | 2022 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $2,936 | $19,500 | Not Implemented |
UL2212 # 04 Y:2022 | 04 | 2022 | USE SOLAR HEAT TO MAKE ELECTRICTY | $34,406 | $237,031 | Not Implemented |
UL2212 # 05 Y:2022 | 05 | 2022 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $7,902 | $63,000 | Not Implemented |
WV0632 # 01 Y:2022 | 01 | 2022 | MINIMIZE WATER USAGE | $12,558 | $11,644 | Not Implemented |
WV0632 # 02 Y:2022 | 02 | 2022 | IMPROVE COMBUSTION CONTROL CAPABILITY | $5,035 | $3,423 | Implemented |
WV0632 # 03 Y:2022 | 03 | 2022 | UPGRADE CONTROLS ON COMPRESSORS | $4,403 | $2,234 | Not Implemented |
WV0632 # 04 Y:2022 | 04 | 2022 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,805 | $706 | Implemented |