IAC logo
Search IAC Recommendations
Sponsored by:
DOE MESC
IAC logo
Search IAC Recommendations
Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.

4,880

matching recommendations
Reset
Row Colors Legend
no implementation information
Implemented
NOT Implemented
ID # Year Products Savings Cost Status
UC2313 # 04 Y:2023 04 2023 INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS $732 $428 n/a
UC2313 # 05 Y:2023 05 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $873 $1,300 n/a
UC2313 # 06 Y:2023 06 2023 UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED $251 $50 n/a
UC2313 # 07 Y:2023 07 2023 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $1,805 $75 n/a
UC2313 # 08 Y:2023 08 2023 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,884 $16,157 n/a
UC2313 # 09 Y:2023 09 2023 MINIMIZE USE OF OUTSIDE MAKE-UP AIR FOR VENTILATION EXCEPT WHEN USED FOR ECONOMIZER CYCLE $4,673 $19,488 n/a
UC2313 # 10 Y:2023 10 2023 INSTALL TIMERS AND/OR THERMOSTATS $615 $1,053 n/a
TT0304 # 01 Y:2023 01 2023 AIR CONDITION ONLY SPACE NECESSARY $74,585 $185,000 Not Implemented
TT0304 # 02 Y:2023 02 2023 BEGIN A PRACTICE OF PREDICTIVE / PREVENTATIVE MAINTENANCE $51,075 $120 Implemented
TT0304 # 03 Y:2023 03 2023 METER RECYCLED WATER (TO REDUCE SEWER CHARGES) $38,784 $10,000 Not Implemented
TT0304 # 04 Y:2023 04 2023 OPTIMIZE PLANT POWER FACTOR $12,488 $40,000 Not Implemented
TT0304 # 05 Y:2023 05 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $8,867 $5 Implemented
TT0304 # 06 Y:2023 06 2023 INSULATE BARE EQUIPMENT $6,857 $372 Implemented
TT0304 # 07 Y:2023 07 2023 UPGRADE CONTROLS ON COMPRESSORS $5,133 $300 Implemented
TT0304 # 08 Y:2023 08 2023 USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM $2,000 $3,000 Not Implemented
TT0304 # 09 Y:2023 09 2023 ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES $544 $405 Implemented
TT0304 # 10 Y:2023 10 2023 UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS $87 $50 Implemented
NT0017 # 01 Y:2023 01 2023 ANALYZE FLUE GAS FOR PROPER AIR/FUEL RATIO $50,287 $1,258 Not Implemented
NT0017 # 02 Y:2023 02 2023 OPTIMIZE PLANT POWER FACTOR $7,255 $2,016 Not Implemented
NT0017 # 03 Y:2023 03 2023 LOWER TEMPERATURE DURING THE WINTER SEASON AND VICE-VERSA $262 $0 Implemented
NT0017 # 04 Y:2023 04 2023 REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED $17,009 $0 Implemented
NT0017 # 05 Y:2023 05 2023 INSULATE BARE EQUIPMENT $1,567 $1,311 Not Implemented
NT0017 # 06 Y:2023 06 2023 INSTALL / REPAIR INSULATION ON STEAM LINES $2,798 $3,380 Not Implemented
NT0017 # 07 Y:2023 07 2023 UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS $734 $2,396 Not Implemented
AS0563 # 01 Y:2023 01 2023 INSTALL HEAT PIPES / RAISE COOLING SETPOINT $24,380 $2,114 Implemented