Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,333
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
AS0286 # 10 Y:2000 | 10 | 2000 | MODIFY STARTUP/SHUTDOWN TIMES | $567 | $120 | Not Implemented |
AR0192 # 01 Y:2000 | 01 | 2000 | OPTIMIZE PLANT POWER FACTOR | $12,065 | $11,950 | Not Implemented |
AR0192 # 02 Y:2000 | 02 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $1,251 | $1,567 | Implemented |
AR0192 # 03 Y:2000 | 03 | 2000 | UTILIZE ENERGY-EFFICIENT BELTS AND OTHER IMPROVED MECHANISMS | $1,515 | $0 | Not Implemented |
AR0192 # 04 Y:2000 | 04 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $492 | $1,426 | Implemented |
AR0192 # 05 Y:2000 | 05 | 2000 | USE WASTE HEAT FROM HOT FLUE GASES TO PREHEAT | $19,496 | $24,000 | Implemented |
AR0192 # 06 Y:2000 | 06 | 2000 | ADD EQUIPMENT/ OPERATORS TO REDUCE PRODUCTION BOTTLENECK | $160,000 | $45,600 | Implemented |
KU0549 # 01 Y:2000 | 01 | 2000 | INSTALL OCCUPANCY SENSORS | $2,352 | $150 | Not Implemented |
KU0549 # 02 Y:2000 | 02 | 2000 | PREVENT EXCESSIVE SOLVENT USAGE (OPERATOR TRAINING) | $2,132 | $3,172 | Implemented |
SF0200 # 01 Y:2000 | 01 | 2000 | REPLACE ELECTRICALLY-OPERATED EQUIPMENT WITH FOSSIL FUEL EQUIPMENT | $2,619 | $2,800 | Not Implemented |
SF0200 # 02 Y:2000 | 02 | 2000 | INSTALL TIMERS ON LIGHT SWITCHES IN LITTLE USED AREAS | $2,726 | $7,750 | Not Implemented |
SF0200 # 03 Y:2000 | 03 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $4,122 | $13,280 | Not Implemented |
SF0200 # 04 Y:2000 | 04 | 2000 | RECOVER AND REUSE WASTE MATERIAL | $24,800 | $0 | Not Implemented |
SF0200 # 05 Y:2000 | 05 | 2000 | INSTALL EQUIPMENT (eg COMPACTOR) TO REDUCE DISPOSAL COSTS | $16,728 | $70,000 | Not Implemented |
ND0363 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,021 | $8,040 | Implemented |
ND0363 # 02 Y:2000 | 02 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $7,260 | $520 | Implemented |
ND0363 # 03 Y:2000 | 03 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $189 | $380 | Not Implemented |
ND0363 # 04 Y:2000 | 04 | 2000 | INSTALL OCCUPANCY SENSORS | $234 | $300 | Not Implemented |
ND0363 # 05 Y:2000 | 05 | 2000 | PAY UTILITY BILLS ON TIME | $1,211 | $0 | Implemented |
ND0364 # 01 Y:2000 | 01 | 2000 | DEVELOP A REPAIR/REPLACE POLICY | $8,340 | $22,377 | Implemented |
ND0364 # 02 Y:2000 | 02 | 2000 | REDUCE ILLUMINATION TO MINIMUM NECESSARY LEVELS | $3,206 | $0 | Implemented |
ND0364 # 03 Y:2000 | 03 | 2000 | INSTALL OCCUPANCY SENSORS | $839 | $600 | Not Implemented |
ND0364 # 04 Y:2000 | 04 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $271 | $575 | Implemented |
ND0364 # 05 Y:2000 | 05 | 2000 | INSTALL COMPRESSOR AIR INTAKES IN COOLEST LOCATIONS | $3,221 | $1,000 | Not Implemented |
ND0364 # 06 Y:2000 | 06 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $75 | $200 | Implemented |