Implementation Grant Funding Opportunity Open
IMPORTANT: The grant program operates on a rolling basis and applications may be submitted at any time, with quarterly reviews.
Learn More
Implementation Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received IAC or Combined Heat and Power Technical Assistance Partnership assessments between 2018 and 2024, can now apply for grants for implementation of assessment recommendations up 50% of qualifying* project costs with a maximum of $300,000 per manufacturer.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
5,333
matching recommendationsRow Colors Legend |
---|
no implementation information |
Implemented |
NOT Implemented |
ID | # | Year | Products | Savings | Cost | Status |
---|---|---|---|---|---|---|
TN0695 # 07 Y:2000 | 07 | 2000 | USE COOLING TOWER OR ECONOMIZER TO REPLACE CHILLER COOLING | $15,015 | $21,850 | n/a |
TN0695 # 08 Y:2000 | 08 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $6,245 | $0 | n/a |
TN0695 # 09 Y:2000 | 09 | 2000 | INSTALL VINYL STRIP / HIGH SPEED / AIR CURTAIN DOORS | $3,800 | $5,510 | n/a |
TN0695 # 10 Y:2000 | 10 | 2000 | INSTALL SPECTRAL REFLECTORS / DELAMP | $2,880 | $1,850 | n/a |
TN0695 # 11 Y:2000 | 11 | 2000 | INSTALL TIMERS AND/OR THERMOSTATS | $2,160 | $2,820 | n/a |
NC0200 # 01 Y:2000 | 01 | 2000 | RECOVER WASTE HEAT FROM EQUIPMENT | $20,439 | $27,000 | n/a |
NC0200 # 02 Y:2000 | 02 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $8,705 | $51,300 | n/a |
NC0200 # 03 Y:2000 | 03 | 2000 | CHILL WATER TO THE HIGHEST TEMPERATURE POSSIBLE | $921 | $1,000 | n/a |
NC0200 # 04 Y:2000 | 04 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $30,871 | $10,600 | n/a |
NC0200 # 05 Y:2000 | 05 | 2000 | METER WASTE WATER | $15,526 | $7,025 | n/a |
ME0298 # 01 Y:2000 | 01 | 2000 | USE ADJUSTABLE FREQUENCY DRIVE OR MULTIPLE SPEED MOTORS ON EXISTING SYSTEM | $35,240 | $66,900 | Implemented |
ME0298 # 02 Y:2000 | 02 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,062 | $5,845 | Not Implemented |
ME0298 # 03 Y:2000 | 03 | 2000 | ELIMINATE LEAKS IN INERT GAS AND COMPRESSED AIR LINES/ VALVES | $1,392 | $340 | Implemented |
ME0298 # 04 Y:2000 | 04 | 2000 | UTILIZE CONTROLS TO OPERATE EQUIPMENT ONLY WHEN NEEDED | $241 | $450 | Not Implemented |
ME0298 # 05 Y:2000 | 05 | 2000 | INSULATE FEEDWATER TANK | $88 | $250 | Not Implemented |
ME0298 # 06 Y:2000 | 06 | 2000 | REDUCE SCRAP PRODUCTION | $61,470 | $204,600 | Not Implemented |
ME0298 # 07 Y:2000 | 07 | 2000 | ADD/MODIFY EQUIPMENT TO IMPROVE DRYING PROCESS | $20,769 | $0 | Not Implemented |
MO0293 # 01 Y:2000 | 01 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $1,962 | $3,520 | Implemented |
MO0293 # 02 Y:2000 | 02 | 2000 | USE MOST EFFICIENT TYPE OF ELECTRIC MOTORS | $443 | $495 | Implemented |
MO0293 # 03 Y:2000 | 03 | 2000 | IMPROVE AIR CIRCULATION WITH DESTRATIFICATION FANS / OTHER METHODS | $21,600 | $52,500 | Not Implemented |
MO0293 # 04 Y:2000 | 04 | 2000 | LEASE / PURCHASE BALER; SELL CARDBOARD TO RECYCLER | $1,170 | $0 | Not Implemented |
MO0293 # 05 Y:2000 | 05 | 2000 | UTILIZE HIGHER EFFICIENCY LAMPS AND/OR BALLASTS | $2,948 | $750 | Not Implemented |
MO0293 # 06 Y:2000 | 06 | 2000 | RE-ARRANGE EQUIPMENT LAYOUT TO REDUCE HANDLING COSTS | $5,897 | $12,000 | Implemented |
SF0201 # 01 Y:2000 | 01 | 2000 | APPLY A PROTECTIVE COATING TO RACKS AND TANKS | $4,646 | $120 | Implemented |
SF0201 # 02 Y:2000 | 02 | 2000 | REDUCE THE PRESSURE OF COMPRESSED AIR TO THE MINIMUM REQUIRED | $1,708 | $25 | Implemented |